MGMT 306 OM Chapters 3-4 Quizzes – Flashcards
Unlock all answers in this set
Unlock answersquestion
the three phases involved in the management of large projects are:
answer
planning, scheduling, and controlling
question
which of the following does NOT belong to the planning phase of project management?
answer
monitoring resources. Which DO belong in the planning phase? -team organization -goal setting -defining the project
question
the project organization may be less helpful when:
answer
the job is familiar to the existing organization. it IS helpful when: -work tasks can be defined with a specific goal and deadline -the work contains complex interrelated tasks requiring specialized skills -the project cuts across organizational lines
question
which of the following is the 3rd level in work breakdown structure?
answer
subtasks in major tasks
question
Gantt charts are:
answer
planning charts used to schedule resources and allocate time
question
which of the following is NOT part of project controlling?
answer
sequencing and allotting time to all project activities which IS part? -shifting resources to where they are needed most -using a feedback loop to revise the project plan -close monitoring of resources, costs, quality, and budgets
question
the critical path of a network is the:
answer
longest time path through the network
question
how is the EF computed?
answer
ES + Activity time
question
which of these time estimates is NOT used in PERT?
answer
standard time which IS: -pessimistic time -most likely time -optimistic time
question
what is the shortest duration required to complete an activity?
answer
crash time
question
which of the following is a limitation of PERT and CPM?
answer
there is the inherent danger of placing too much emphasis on the critical path
question
among the following, critical path and slack time analysis MOST help:
answer
pinpoint activities that need to b closely watched
question
what is the most popular example of specialized software for managing projects?
answer
microsoft project
question
computerized PERT/CPM reports and charts do not include:
answer
probability estimates for on-time completion -they DO include: detailed cost breakdowns for each task -variance reports -cost distribution tables
question
the latest finish of an activity is:
answer
Min (LS of all immediate following activities)
question
which of the following is a direct responsibility of the project manager?
answer
making sure that the people assigned to the project receive the motivation, direction, and information needed to do their jobs
question
which column in Microsoft Project defines the precedence relationships among the activities?
answer
predecessors
question
the most realistic estimate of the time required to complete an activity is referred to as
answer
most likely time
question
which of the following is used for computations in CPM?
answer
normal time
question
which of the following is not a technique that allows managers to plan, schedule, and control projects?
answer
factor rating method which are techniques? -CPM -PERT -Gantt charts
question
which of the following is an advantage of PERT and CPM?
answer
straightforward and not mathematically complex
question
which of the following activities are NOT part of project scheduling?
answer
make sure all necessary activities are finished in proper sequence and on time which ARE part of project scheduling? -decide how long each activity will take -compute resources needed at each stage of production -chart separate schedules for personnel needs by type of skill and material needs
question
which of the following is NOT true about Gantt charts?
answer
Gantt charts qeduately illustrate the interrelationships between the activities and the resources. which IS true: -they are planning charts used to schedule resources and allocate time -they are low cost mean of helping managers make sure that activities are planned -they also can be used for scheduling repetitive operations
question
the forecasting time horizon that would typically be easiest to predict for would be the
answer
short range
question
a forecast that projects a company's sales is
answer
a demand forecast
question
CPFR is
answer
collaborative, planning, forecasting, and replenishment
question
which of the follwing statements is NOT true?
answer
when excess capacity exists, costs can decrease which IS true? -when capacity is inadequate, customers can be lost -when capacity is inadequate, market share can shrink -when excess capacity exists, cost can increase
question
which of the following is the FIRST step in a forecasting system?
answer
determine the use of the forecast
question
which of the following forecasting steps comes directly after determining the time horizon of the forecast?
answer
select the forecasting model(s)
question
which of the following is a quantitative forecasting method?
answer
exponential smoothing qualitative methods? -market survey sales force composite jury of executive opinion
question
which forecasting model is based upon salespersons estimates of expected sales?
answer
sales force composite
question
what is a data pattern that repeats itself after a period of days, weeks, months, or quarters?
answer
seasonality
question
which forecasting method considers several variables that are related to the variable being predicted?
answer
multiple regression
question
a tracking signal
answer
is a measurement of how well a forecast is predicting actual values
question
which of the following statements is NOT true about the forecasting in the service sector?
answer
detailed forecasts of demand are not needed which IS true about the service sector? -forecasting in the service sector presents some unusual challenges -demand patterns are often different from those in non service sectors hourly demand forecasts may be necessary
question
when using exponential smoothing, the smoothing constant
answer
can be determined using MAD
question
a measure of strength of the relationship between two variables is referred to as
answer
coefficient of correlation
question
a consistent tendency for forecasts to be greater of less than the actual values is called a ________ error
answer
bias
question
which of the following is the FINAL step in a forecasting system?
answer
validate and implement the results
question
a forecast that addresses the business cycle by predicting planning indicators is
answer
an economic forecast
question
which of the following is not a time-series model?
answer
linear regression what IS a time series model: -moving averages -naive approach -exponential smoothing
question
which of the following is a qualitative forecasting method?
answer
Delphi method
question
the goal of CPFR is to:
answer
create significantly more accurate information that can power the supply chain
question
which of the following is NOT true regarding forecasting?
answer
forecasting is exclusively an objective prediction