question
A(n) _____ on a project is a significant event that normally has no duration.
answer
milestone
question
An IT company revises its process parameters in response to complaints from vendors that products were not ready on time. This would be an example of _____.
answer
a corrective action
question
Which of the following are organizational process assets?
answer
assets include formal and informal plans, policies, procedures, guidelines, information systems, financial systems, management systems, lessons learned, and historical information that can influence a project's success.
question
Which of the following statements is true of project management?
answer
It does not guarantee successes for all projects.
question
The outputs of the _____ process include change request status updates, project management plan updates, and project document updates.
answer
monitoring and controlling
question
The _____ section of the project management plan describes specific methodologies a project might use and explains how to document information.
answer
technical processes
question
Which of the following refers to a set of principles that guides decision making based on personal values of what is considered right and wrong?
answer
ethics
question
Which of the following is true of return on investment or ROI?
answer
it is always a percentage
question
Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?
answer
project charter
question
Which of the following is true of a finsih-to-finish dependency?
answer
It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.
question
Which of the following is true of the agile approach to software development?
answer
In the agile method, requirements and solutions evolve through collaboration
question
Project procurement management primarily involves identifying stakeholder needs while managing their engagement throughout the life of the project.
answer
false
question
In project time management, the process of_____ primarily involves checking and managing changes to the project schedule.
answer
controlling the schedule
question
A _____ is a tool used in quality management.
answer
checklist
question
The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____.
answer
free slack
question
The first step in the planning process is _____.
answer
to choose which projects to do and assigning resources to work on them
question
A network diagramming technique in which boxes represent activities is known as a(n) _____.
answer
PDM
question
A Gantt chart is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a ____ format
answer
calendar
question
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float
answer
longest and shortest
question
Payback occurs when
answer
the net cumulative benefits equal the net cumulative costs.
question
Validated changes and validated deliverables are the outputs of the _____ subprocess of project quality management
answer
monitoring and controlling
question
The formula to determine the number of communication channels is _____, where n is the number of people involved.
answer
n(n-1)/2
question
The project team must take corrective action if stakeholders with high interest and high power are categorized as _____.
answer
resistant
question
Which of the following is true about identifying stakeholder?
answer
Stakeholders with indirect ties to the project need not be engaged with.
question
Using the formula for calculating the number of communication channels, how many channels would five people require?
answer
10
question
After identifying and analyzing stakeholders, the project manager and team should develop a(n) ______ to help them effectively engage stakeholders and make sure that good decisions are made throughout the life of the project.
answer
stakeholder management plan
question
The capacity to understand the motivations, intentions and desires of others is
answer
interpersonal intelligence
question
The main outputs of the _____ process are team performance assessments and enterprise environmental factors updates.
answer
developing the project team
question
Which of the following is a guideline that project managers should follow when communicating with their teams through e-mail?
answer
If the entire message can fit in the subject line, put it there.
question
_____ helps integrate traditionally separate organizational functions, set process improvement goals and priorities, provide guidance for quality processes, and provide a point of reference for appraising current processes.
answer
CMMI
question
_____ involves using punishment, threats, or other negative approaches to get people to do things they do not want to do
answer
coercive power
question
_____ applies to positive risks when the project team cannot or chooses not to take any actions toward a risk.
answer
Risk Acceptance
question
_____ involves determining everyone involved in the project or affected by it, and determining the best ways to manage relationships with them.
answer
Identifying stakeholders
question
One of the main outputs of the process are the issue logs
answer
managing stakeholder engagement
question
_____ address where the project stands in terms of meeting scope, time, and cost goals.
answer
Status reports
question
A(n) _____ is a column chart that shows the number of resources assigned to a project over time.
answer
resource histogram
question
_____ involves deciding how to approach and plan the risk management activities for the project.
answer
Planning risk management
question
The stakeholder register is the output of the _____ process of project stakeholder management
answer
executing
question
Performing qualitative and quantitative risk analyses are subprocesses of the _____ process of project risk management
answer
planning
question
Recognizing an employee as the "Star Performer of the Month" would be satisfying the _____ need of the Maslow's hierarchy of needs.
answer
esteem
question
Six Sigma's target for perfection is the achievement of no more than _____ defects, errors, or mistakes per million opportunities
answer
3.4
question
_____ is a technique for resolving resource conflicts by delaying tasks.
answer
resource leveling
question
Doctors who have been co-opted to actively participate in a project related to using information technology for chronic health problems would be examples of _____ stakeholders.
answer
leading
question
_____ addresses the ease of performing maintenance on a product
answer
maintainability
question
____ describe what the project team has accomplished during a certain period.
answer
progess reports
question
_____ involves allocating ownership of the risk to another party
answer
Risk sharing
question
A(n) _____ refers to a product or service, such as a technical report, a training session, a piece of hardware, or a segment of software code, produced or provided as part of a project.
answer
deliverable
question
_____ are an example of external stakeholders for an organization.
answer
competitors
question
Project procurement management mainly involves:
answer
buying goods and services for a project from outside the performing organization.
question
Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
answer
feeding buffers
question
In organizational culture, people focus refers to _____.
answer
the degree to which management's decisions take into account the effect of outcomes on employees within the organization
question
Which of the following is true of the project life cycle?
answer
In the early phases of a project life cycle, resource needs are usually lowest.
question
A _____ is an organizational group responsible for coordinating the project management function throughout an organization.
answer
Project Management Office
question
Which of the following dependencies involve relationships between project and non-project activities?
answer
External
question
In the _____ model, developers use a model to generate functional requirements and physical design specifications simultaneously.
answer
prototyping life cycle
question
In which of the following areas of management is payback analysis most likely to be used?
answer
cost
question
After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to:
answer
estimate the duration of activities.
question
Project _____ management ensures that the project will satisfy the stated or implied needs for which it was undertaken.
answer
quality
question
In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work
answer
defining activities
question
The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____.
answer
crashing
question
Which of the following is an output of schedule control?
answer
Lessons-learned reports
question
Which of the following is a difference between projects and operations?
answer
Projects are temporary endeavors whereas an organization's operations are ongoing in nature.
question
Those who are _____ have a higher tolerance for risk, and their satisfaction increases when more payoff is at stake
answer
risk-seeking
question
_____ involves eliminating a specific threat, usually by eliminating its causes.
answer
Risk avoidance
question
A _____ is a graphic display of data that illustrates the results of a process over time
answer
control chart
question
_____ involves doing whatever you can to make sure the positive risk happens
answer
Risk exploitation
question
The _____ process is often associated with the technical tools and techniques of quality management, such as Pareto charts, quality control charts, and statistical sampling.
answer
quality control
question
_____ is the degree to which a system performs its intended function
answer
Functionality
question
An example of push communication is _____.
answer
voice mails
question
Performing quality assurance is a subprocess of the _____ process of project quality management.
answer
executing
question
_____ analysis simulates a model's outcome many times to provide a statistical distribution of the calculated results.
answer
monte carlo
question
At the bottom of Maslow's structure are _____ needs
answer
physiological
question
_____ means that a product can be used as it was intended.
answer
Fitness for use
question
_____ involves determining which risks are likely to affect a project and documenting the characteristics of each.
answer
Identifying risks
question
Key outputs of _____ process are project staff assignments, resource calendars, and project management plan updates
answer
managing the project team
question
_____ is the new knowledge area identified by the Project Management Institute.
answer
Project stakeholder management
question
_____ are unplanned responses to risk events used when project teams do not have contingency plans in place
answer
workarounds
question
_____ involves monitoring stakeholder relationships and adjusting plans and strategies for engaging stakeholders as needed.
answer
Controlling stakeholder engagement
question
_____, a quality system standard is a three-part, continuous cycle of planning, controlling, and documenting quality in an organization
answer
ISO 9000
question
Managers who follow _____ assume that the average worker wants to be directed and prefers to avoid responsibility.
answer
Theory X
question
According to McClelland's acquired-needs theory, people with a high need for _____ desire harmonious relationships with other people and need to feel accepted by others.
answer
affiliation
question
_____ is based on an individual's personal charisma
answer
referent power
question
In the Tuckman model, _____ occurs when the emphasis is on reaching the team goals, rather than working on team process
answer
performing
question
A ____ is a bell-shaped curve that is symmetrical regarding the average value of the population (the data being analyzed).
answer
normal
question
According to Herzberg, which of the following is a motivational factor?
answer
Recognition
question
A(n) _____ is any instance where the product or service fails to meet customer requirements
answer
defect
question
_____ are/is a qualitative risk analysis tool that maintains an awareness of risks throughout the life of a project in addition to identifying risks
answer
Top Ten Risk Item Tracking