planning schedule management
answer
The first process involved in project time management is _____ .
question
Defining activities
answer
Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?
question
Defining activities
answer
In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list?
question
Sequencing activities
answer
In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities?
question
Estimating activity durations
answer
In project time management, which of the following processes involve calculating the number of work periods that are needed to complete individual activities?
Unlock the answer
question
Developing the schedule
answer
In project time management, which of the following processes involve analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?
Unlock the answer
question
controlling the schedule
answer
In project time management, the process of_____ primarily involves checking and managing changes to the project schedule.
Unlock the answer
question
project management plan update
answer
In project time management, a(n) _____ is an output of controlling the schedule
Unlock the answer
question
Project charter
answer
Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?
Unlock the answer
question
An activity attribute provides more schedule-related information about each activity than an activity list.
answer
Which of the following is a difference between an activity list and an activity attribute?
Unlock the answer
question
milestone
answer
A(n) _____ on a project is a significant event that normally has no duration.
Unlock the answer
question
defining activities
answer
In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.
Unlock the answer
question
determining their dependencies.
answer
In project time management, the next step after defining project activities is:
Unlock the answer
question
Mandatory
answer
Which of the following types of dependencies are inherent in the nature of work being performed on a project?
Unlock the answer
question
Discretionary
answer
_____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.
Unlock the answer
question
External
answer
Which of the following dependencies involve relationships between project and non-project activities?
Unlock the answer
question
bursts
answer
In an AOA network diagram, _____ occur when two or more activities follow a single node.
Unlock the answer
question
PDM
answer
A network diagramming technique in which boxes represent activities is known as a(n) _____.
Unlock the answer
question
finish-to-start
answer
AOA network diagrams use only _____ dependencies.
Unlock the answer
question
Start-to-start
answer
Which of the following is a relationship in which the "from" activity cannot start until the "to" activity is started?
Unlock the answer
question
It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.
answer
Which of the following is true of a finsih-to-finish dependency?
Unlock the answer
question
They show logical relationships between activities.
answer
Which of the following is true of dummy activities?
Unlock the answer
question
Project documents update
answer
Which of the following is one of the main outputs of estimating activity resources process?
Unlock the answer
question
estimate the duration of activities.
answer
After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to:
Unlock the answer
question
developing a schedule
answer
In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the time dimension of the project.
Unlock the answer
question
Gantt charts
answer
_____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.
Unlock the answer
question
Critical path analysis
answer
Which of the following is a network diagramming technique used primarily to predict total project duration?
Unlock the answer
question
longest; shortest
answer
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.
Unlock the answer
question
free slack
answer
The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____.
Unlock the answer
question
Total slack
answer
_____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.
Unlock the answer
question
late start date
answer
The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.
Unlock the answer
question
crashing
answer
The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____.
Unlock the answer
question
Fast tracking
answer
Which of the following techniques involve doing activities in parallel that one would normally do in sequence?
Unlock the answer
question
both can shorten the time needed to finish a project.
answer
A similarity between the crashing technique and the fast tracking technique is that:
Unlock the answer
question
feeding buffers
answer
Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
Unlock the answer
question
Parkinson's Law
answer
_____ states that work expands to fill the time allowed.
Unlock the answer
question
PERT uses different duration estimates whereas CPM uses one specific duration estimate.
answer
A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that:
Unlock the answer
question
Both are portions of the integrated change control process under project integration management.
answer
Which of the following is a similarity between scope control and schedule control?
Unlock the answer
question
Lessons-learned reports
answer
Which of the following is an output of schedule control?
Unlock the answer
question
project charter
answer
A draft schedule for a project is most likely to be found in a _____.
Unlock the answer
question
True
answer
Many information technology projects are failures in terms of meeting scope, time, and cost projections. T/F
Unlock the answer
question
False
answer
Managers often cite cost issues during the end phase of a project as one of their biggest challenges and the main cause of conflict. T/F
Unlock the answer
question
True
answer
Schedule performance can be estimated by subtracting the original timeestimate from how long it really took to complete the project. T/F
Unlock the answer
question
True
answer
Individual work styles and cultural differences may cause schedule conflicts. T/F
Unlock the answer
question
True
answer
Different cultures may have different perceptions of work ethic. T/F
Unlock the answer
question
False
answer
The outputs to schedule development include activity duration estimates and project document updates. T/F
Unlock the answer
question
False
answer
The main outputs of estimating activity resources include the activity list and attributes, project scope statement, milestone list, and organizational process assets. T/F
Unlock the answer
question
False
answer
Most managers are unfamiliar with any forms of scheduling. T/F
Unlock the answer
question
True
answer
Project schedules grow out of the basic documents that initiate a project. T/F
Unlock the answer
question
False
answer
It only takes one activity to complete a milestone. T/F
Unlock the answer
question
False
answer
Activity information is not a required input to the other time management processes. T/F
Unlock the answer
question
True
answer
After defining project activities, the next step in project time management is sequencing them or determining their dependencies. T/F
Unlock the answer
question
True
answer
Even though the delivery of new hardware may not be in the scope of a project, you should add an external dependency to it if required project activities depend on that delivery. T/F
Unlock the answer
question
False
answer
Network diagrams are the preferred technique for showing activitydiscretionary dependencies. T/F
Unlock the answer
question
True
answer
The arrows in a network diagram represent the activity sequencing or relationships between tasks. T/F
Unlock the answer
question
False
answer
It is not necessary to complete all of the activities on the network diagram in order for the project to finish. T/F
Unlock the answer
question
False
answer
Every item on the WBS needs to be on the network diagram. T/F
Unlock the answer
question
False
answer
Start-to-finish relationships are the most common type of relationships. T/F
Unlock the answer
question
True
answer
It is important that the people who help determine what resources arenecessary include people who have experience and expertise in similar projects and with the organization performing the project. T/F
Unlock the answer
question
False
answer
Duration only includes the actual amount of time worked on an activity. T/F
Unlock the answer
question
True
answer
In a Gantt chart created in Microsoft Project, a black diamond symbol represents a milestone. T/F
Unlock the answer
question
True
answer
A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates. T/F
Unlock the answer
question
False
answer
Most projects have one path through a network diagram. T/F
Unlock the answer
question
False
answer
The critical path always includes the most critical activities. T/F
Unlock the answer
question
True
answer
A fast and easy way to determine early and late start and finish dates and free and total slack amounts for activities is by using project management software. T/F
Unlock the answer
question
True
answer
Fast tracking can end up lengthening the project schedule. T/F
Unlock the answer
question
False
answer
By using the PERT weighted average for each activity duration estimate,the total project duration estimate does not account for the risk or uncertainty in the individual activity estimates. T/F
Unlock the answer
question
True
answer
One of PERT's main disadvantages is that it involves more work than CPM. T/F
Unlock the answer
question
True
answer
Many projects, especially in information technology, have very unrealistic schedule expectations. T/F
Unlock the answer
question
False
answer
Project management software does not have the capacity to automatically generate network diagrams and calculate the critical path(s) for the project. T/F
Unlock the answer
question
six
answer
There are __ main processes involved in project time management.
Unlock the answer
question
defining activities
answer
The main outputs of the ____ process are an activity list, activity attributes, and milestone list
Unlock the answer
question
sequencing activites
answer
___ involves identifying and documenting the relationships between project activities
Unlock the answer
question
estimating activity durations
answer
____ involves estimating the number of work periods that are needed tocomplete individual activities
Unlock the answer
question
developing the schedule
answer
____ involves analyzing activity sequences, activity resource estimates, andactivity duration estimates to create the project schedule.
Unlock the answer
question
activity attributes
answer
The ____ provide(s) schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.
Unlock the answer
question
defining activities
answer
he goal of ____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.
Unlock the answer
question
defining activities
answer
____ results in supporting detail to document important product information as well as assumptions and constraints related to specific activities
Unlock the answer
question
sequencing activities
answer
____ involves evaluating the reasons for dependencies and the different types of dependencies.
Unlock the answer
question
mandatory
answer
____ dependencies are inherent in the nature of the work being performed on a project.
Unlock the answer
question
discretionary
answer
____ dependencies are sometimes referred to as soft logic and should be used with care since they may limit later scheduling options.
Unlock the answer
question
external
answer
____ dependencies involve relationships between project and non-project activities
Unlock the answer
question
bursts
answer
___ occur when two or more activities follow a single node.
Unlock the answer
question
right
answer
On a network diagram, all arrowheads should face toward the ___
Unlock the answer
question
PDM
answer
he ____ is a network diagramming technique in which boxes represent activities
Unlock the answer
question
finish to start
answer
In a ____ relationship, the "from" activity must finish before the "to" activity can start
Unlock the answer
question
start to start
answer
In a ____ relationship, the "from" activity cannot start until the "to" activity is started.
Unlock the answer
question
finish to finish
answer
In a ____ relationship, one task cannot finish before another finishes.
Unlock the answer
question
resource breakdown structure
answer
A ____ is a hierarchical structure that identifies the project's resources by category and type.
Unlock the answer
question
duration estimates
answer
The activity list, activity attributes, activity resource requirements, resource calendars, project scope statement, enterprise environmental factors, and organizational process assets all include information that affect ____
Unlock the answer
question
developing the schedule
answer
The ultimate goal of ____ is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project.
Unlock the answer
question
Gantt charts
answer
____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format
Unlock the answer
question
critical path analysis
answer
___ is a network diagramming technique used to predict total project duration.
Unlock the answer
question
longest; shortest
answer
The critical path is the ____ path through a network diagram, and it represents the ____ time it takes to complete a project
Unlock the answer
question
free slack
answer
____ is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.
Unlock the answer
question
total slack
answer
___ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.
Unlock the answer
question
late start date
answer
he ____ for an activity is the latest possible time an activity might begin without delaying the project finish date
Unlock the answer
question
crashing
answer
____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.
Unlock the answer
question
fast tracking
answer
__ involves doing activities in parallel that you would normally do in sequence.
Unlock the answer
question
critical chain scheduling
answer
_ is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.
Unlock the answer
question
feeding buffers
answer
Critical chain scheduling protects tasks on the critical chain from being delayed by using ____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks
Unlock the answer
question
parkinson's law
answer
___ states that work expands to fill the time allowed
Unlock the answer
question
PERT
answer
___ use(s) probabilistic time estimates duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations instead of one specific or discrete duration estimate.
Unlock the answer
question
schedule control
answer
The goal of ____ is to know the status of the schedule, influence the factors that cause schedule changes, determine that the schedule has changed, and manage changes when they occur
Unlock the answer
question
tracking gantt chart
answer
project managers often illustrate progress with a ____ showing key deliverables and activities
Unlock the answer
question
project schedules
answer
Project managers must use discipline to control __
Unlock the answer
question
red
answer
Project management software highlights the critical path in ____ on a network diagram
Unlock the answer
question
time
answer
______________ is the one variable in project scheduling that has the least amount of flexibility
Unlock the answer
question
project time management
answer
_________________ involves the processes required to ensure timely completion of a project.
Unlock the answer
question
estimating activity resources
answer
_________________ involves estimating how many people, equipment, and materials a project team should use to perform project activities
Unlock the answer
question
estimating activity durations
answer
Outputs of ______________________________ include activity duration estimates and project document updates
Unlock the answer
question
activity list
answer
The ____________________ is a tabulation of activities to be included on a project schedule
Unlock the answer
question
network diagram
answer
A(n) ____________________ is a schematic display of the logical relationships among, or sequencing of, project activities
Unlock the answer
question
node
answer
In a network diagram, a(n) ____________________ is simply the starting and ending point of an activity
Unlock the answer
question
dummy activities
answer
________________ have no duration and no resources but are occasionally needed on AOA network diagrams to show logical relationships between activities
Unlock the answer
question
effort
answer
____________ is the number of workdays or work hours required to complete a task.
Unlock the answer
question
three point estimate
answer
Duration estimates are often provided as a discrete number, such as four weeks, or as a range, such as three to five weeks, or as a(n) __________________
Unlock the answer
question
slipped milestone
answer
A white diamond on the Tracking Gantt chart represents a(n) ___________________
Unlock the answer
question
critical path
answer
A(n) ____________________ for a project is the series of activities that determine the earliest time by which the project can be completed
Unlock the answer
question
forward pass
answer
A(n) ____________________ determines the early start and early finish dates for each activity
Unlock the answer
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New