Chapter 7 Risk Management – Flashcards

Unlock all answers in this set

Unlock answers
question
A) The plans that have been made to deal with problems as they arise.
answer
1) The difference between projects that fail and those that are ultimately successful has to do with: A) The plans that have been made to deal with problems as they arise. B) The fact that a successful project doesn't encounter problems. C) Whether the project is for an internal or external customer. D) Whether the problem is time- or budget-related.
question
B) Concept stage of the project life cycle.
answer
2) Project risk is highest during the: A) Termination stage of the project life cycle. B) Concept stage of the project life cycle. C) Implementation stage of the project life cycle. D) Development stage of the project life cycle.
question
C) Termination stage of the project life cycle.
answer
3) Project risk is lowest during the: A) Concept stage of the project life cycle. B) Implementation stage of the project life cycle. C) Termination stage of the project life cycle. D) Development stage of the project life cycle.
question
D) Termination stage of the project life cycle.
answer
4) The period of highest risk impact for a project risk exists primarily in the: A) Development stage of the project life cycle. B) Concept stage of the project life cycle. C) Implementation stage of the project life cycle. D) Termination stage of the project life cycle.
question
A) The probability of the event is high and the consequences of the event are high.
answer
5) The greatest project risk occurs when: A) The probability of the event is high and the consequences of the event are high. B) The probability of the event is high and the consequences of the event are low. C) The probability of the event is low and the consequences of the event are high. D) The probability of the event is low and the consequences of the event are low.
question
A) The project is in the concept phase.
answer
6) The greatest project opportunity occurs when: A) The project is in the concept phase. B) The project is in the development phase. C) The project is in the implementation phase. D) The project is in the termination phase.
question
D) Termination phase.
answer
7) The amount a company has at stake in a project rises above the dollar value of opportunity in the: A) Implementation phase. B) Development phase. C) Concept phase. D) Termination phase.
question
C) Both decrease throughout the project life cycle.
answer
8) Risk and opportunity: A) Both increase throughout the project life cycle. B) Vary inversely throughout the project life cycle. C) Both decrease throughout the project life cycle. D) Do not vary throughout the project life cycle.
question
C) Low in probability and high in consequence.
answer
9) To protect his poultry from meteorites, the gentleman farmer made hard hats for each bird and installed a meteor detection system that opened umbrellas throughout the yard if a meteor were detected. The safety of his flock thus assured, the farmer was surprised when he read his latest issue of Risk Management Magazine and discovered that this event was: A) High in consequence and high in probability. B) Low in consequence and low in probability. C) Low in probability and high in consequence. D) High in probability and low in consequence.
question
D) High in probability and low in consequence.
answer
10) Jim knew instinctively that his professor wouldn't appreciate it if he brought his single scoop of vanilla ice cream into the lecture hall with him. He could almost hear the inevitable question, "Did you bring enough for everyone?" To avert such an embarrassment, he practically inhaled his frozen confection as he raced down the hall. He had eaten ice cream in this fashion before and knew he would soon have an ice cream headache, which could be described as: A) High in consequence and high in probability. B) Low in consequence and low in probability. C) Low in probability and high in consequence. D) High in probability and low in consequence.
question
A) High in consequence and high in probability.
answer
11) While thrilling, there is a chance that you would have an accident if you elected to drive on the wrong side of a divided highway in Woodward, an outcome that could be described as: A) High in consequence and high in probability. B) Low in consequence and low in probability. C) Low in probability and high in consequence. D) High in probability and low in consequence.
question
B) Four-stage process.
answer
12) Risk management is a: A) Three-stage process. B) Four-stage process. C) Five-stage process. D) Six-stage process.
question
B) Risk mitigation.
answer
13) The construction foreman posted a large sign requiring all work site visitors to don a hard hat and safety glasses. He also purchased copious quantities of both items and made them readily available at the entrance. The foreman is engaged in: A) Risk identification. B) Risk mitigation. C) Analysis of probability and consequences. D) Control and documentation.
question
C) Analysis of probability and consequences phase of risk management.
answer
14) The residents of Enumclaw, Washington, live in the shadow of majestic Mount Rainier and its 26 glaciers. The Cascades form a ring of fire around the Pacific Northwest and erupt with surprising regularity, although Mount Rainier hasn't erupted on a major scale since about a thousand years ago. When it does erupt, the pyroclastic flow (a massive cloud of superheated ash and rock up to 1500 degrees Fahrenheit that can travel at speeds up to 300 miles per hour) will make Enumclaw a less pleasant place to live. City leaders have completed the: A) Control and documentation phase of risk management. B) Risk identification phase of risk management. C) Analysis of probability and consequences phase of risk management. D) Risk mitigation strategies phase of risk management.
question
D) Integration risk.
answer
15) The marketing team would develop the advertising campaign to promote the newest product but the engineers wanted to keep all product details a secret during development. The service and operations branches of the company were also in the dark, so product rollout was going to be their initiation as well. This project has a very high: A) Political risk. B) Operating risk. C) Organizational risk. D) Integration risk.
question
C) Acts of God had come true.
answer
16) The house had almost been framed when an F-5 tornado ripped across the plains and turned the house back into a lumber pile, albeit not stacked as neatly as it was originally. The homeowner's fears of: A) Technical risks had come true. B) Operating risks had come true. C) Acts of God had come true. D) Environmental risks had come true.
question
A) A high consequence and a medium likelihood.
answer
17) A serious risk factor probably has: A) A high consequence and a medium likelihood. B) A high consequence and a low likelihood. C) A medium consequence and a low likelihood. D) A low consequence and a medium likelihood.
question
D) Technical risk.
answer
18) The mouse executive board meeting was drawing to a conclusion; the only way they would be able to detect the presence of the cat was to tie a bell around its tail. Under their risk management identification scheme, this would fall under: A) Commercial risk. B) Execution risk. C) Financial risk. D) Technical risk.
question
B) The Delphi method.
answer
19) A method for conducting risk factor identification that consolidates the judgments of isolated anonymous respondents is: A) A brainstorming meeting. B) The Delphi method. C) Past history. D) Multiple assessments.
question
A) A brainstorming meeting.
answer
20) A method for conducting risk factor identification that generates ideas but doesn't focus on decision making is: A) A brainstorming meeting. B) The Delphi method. C) Past history. D) Multiple assessments.
question
C) Past history.
answer
21) One source of information on future risks and the leading indicators that accompany risks is: A) A brainstorming meeting. B) The Delphi method. C) Past history. D) Multiple assessments.
question
D) A multiple assessments approach to risk factor identification.
answer
22) The terpsichorean was familiar with the risks associated with various moves, the accountant knew financial risks forwards and backwards, while the civil engineer could quantify the risks associated with distributed loads on the temporary stage. Their input was used as part of: A) A brainstorming meeting approach to risk factor identification. B) The Delphi method approach to risk factor identification. C) A past history approach to risk factor identification. D) A multiple assessments approach to risk factor identification.
question
A) Financial risk
answer
23) The probability that project revenues will NOT be sufficient to repay the debts is: A) Financial risk B) Cost estimate risk. C) Market risk. D) Promotion risk.
question
B) Cost estimate risk.
answer
24) The probability that funds allocated to the project will be insufficient to complete it is: A) Technical risk. B) Cost estimate risk. C) Financing risk. D) Operating risk.
question
A) Promotion risk.
answer
25) The probability that investments made to fund the front-end activities will be lost due to project abandonment is: A) Promotion risk. B) Political risk. C) Organizational risk. D) Financial risk.
question
B) Market risk.
answer
26) There is always a chance that the music loving public cannot be convinced of the need to return to the 8-track format for new releases. The probability that we don't sell one million units before the holiday season is: A) Promotion risk. B) Market risk. C) Organizational risk. D) Financial risk.
question
D) Market risk.
answer
27) Based on the projected selling price of $20 per unit, the manufacturer invested a substantial portion of its available cash in a machine that could produce twenty-thousand gumballs in an hour. If consumers weren't willing to pay this much for gum, then the manufacturer faced significant: A) Financial risk. B) Promotion risk. C) Cost estimate risk. D) Market risk.
question
C) Organizational risk.
answer
28) The probability that legal and managerial structures put together to develop and operate the project will NOT perform well is: A) Operating risk. B) Political risk. C) Organizational risk. D) Integration risk.
question
A) Political risk.
answer
29) The probability that a project to establish infrastructure in a third-world country teetering on the brink of civil war is fraught with: A) Political risk. B) Operating risk. C) Organizational risk. D) Integration risk.
question
D) Schedule risk.
answer
30) The probability that a project will overrun its allocated duration is: A) Volume market risk. B) Price market risk. C) Integration risk. D) Schedule risk.
question
C) Greater than 0.56 but less than or equal to 0.89.
answer
31) A project team assesses their primary risk factor's probability of failure with a maturity risk of 0.3, a complexity risk of 0.7, and a dependency risk of 0.8. The probability of failure is: A) Less than or equal to 0.3. B) Greater than 0.3 but less than or equal to 0.55. C) Greater than 0.56 but less than or equal to 0.89. D) Greater than or equal to 0.9.
question
B) About 0.4.
answer
32) With a maturity risk of 0.3, a complexity risk of 0.4, and a dependency risk of 0.5, the probability of failure is: A) About 0.3. B) About 0.4. C) About 0.5. D) About 0.6.
question
A) 0.23.
answer
33) A project team assigns probabilities of 0.1, 0.2, and 0.4 respectively to the maturity, complexity, and dependency categories. The probability of failure can be calculated as: A) 0.23. B) 0.33. C) 0.65. D) 0.70
question
C) 0.4
answer
34) The consequences of failure categories of cost, schedule, reliability, and performance were believed to be 0.25, 0.35, 0.45, and 0.55. What is the overall consequence of failure? A) 0.2 B) 0.3 C) 0.4 D) 0.5
question
D) 0.625 for the squidproofing project.
answer
35) With a cost factor of 0.8, a schedule rating of 0.6, a reliability rating of 0.5, and a performance rating of 0.6, the overall consequence of failure was: A) 0.565 for the squidproofing project. B) 0.500 for the squidproofing project. C) 0.750 for the squidproofing project. D) 0.625 for the squidproofing project.
question
B) 0.107
answer
36) The overall consequence of failure was 0.4 and curiously enough, the consequence of performance is twice that of reliability; the consequence of reliability is twice that of schedule; and the consequence of schedule is twice that of cost. What is the consequence of failure cost? A) 0.091 B) 0.107 C) 0.123 D) 0.136
question
D) Greater than 0.9
answer
37) The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below. What is the overall risk factor for the project? A) Less than or equal to 0.7 B) Greater than 0.7 but less than or equal to 0.8 C) Greater than 0.8 but less than or equal to 0.9 D) Greater than 0.9 Maturity 0.7 Cost 0.4 Complexity 0.6 Schedule 0.6 Dependency 0.8 Reliability 0.8 Performance 0.9
question
C) 0.236
answer
38) The overall risk factor for the project is known to be 0.5. The individual failure probability and consequence scores are not known with certainty, only that all of the failure probability scores are identical and all of the consequence scores are identical. What are the individual failure probability scores? A) 0.316 B) 0.267 C) 0.236 D) 0.347 Maturity X Cost Y Complexity X Schedule Y Dependency X Reliability Y Performance Y
question
A) 0.026
answer
39) The overall project risk factor is known to be 0.5. The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure. The consequence of performance failure is twice the consequence of reliability failure, four times the consequence of schedule failure and eight times the consequence of cost failure. What is the difference between the probability of maturity failure and the consequence of cost failure? A) 0.026 B) 0.033 C) 0.041 D) 0.048 Maturity X Cost Y Complexity 2X Schedule 2Y Dependency 4X Reliability 4Y Performance 8Y
question
D) 0.148
answer
40) The overall project risk factor is known to be 0.6. The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure. The consequence of performance failure is twice the consequence of reliability failure, four times the consequence of schedule failure and eight times the consequence of cost failure. What is the probability of maturity failure? A) 0.213 B) 0.197 C) 0.104 D) 0.148 Maturity X Cost Y Complexity 2X Schedule 2Y Dependency 4X Reliability 4Y Performance 8Y
question
A) Greater than 0.7
answer
41) Use the failure probability and consequence scores shown in the table to determine the consequence of failure for the project. A) Greater than 0.7 B) Less than or equal to 0.7 but greater than 0.5 C) Less than or equal to 0.5 but greater than 0.3 D) Less than 0.2 Maturity 0.6 Cost 0.2 Complexity 0.8 Schedule 0.3 Dependency 0.6 Reliability 0.2 Performance 0.5
question
D) Accept it.
answer
42) If the risk of a negative outcome is slight, the BEST course of action might be to: A) Minimize it. B) Share it. C) Transfer it. D) Accept it.
question
B) Minimize risk.
answer
43) The professor wore both a belt and suspenders during lecture each day because he chose to: A) Accept risk. B) Minimize risk. C) Share risk. D) Transfer risk.
question
C) Transfer risk.
answer
44) Fred Knievel took out a substantial life insurance policy before he began his trek across North America in his Volvo. Doing so enabled him to: A) Accept risk. B) Minimize risk. C) Transfer risk. D) Share risk.
question
A) Accept the risk.
answer
45) The Farm Fresh Egg project was too great for one person to pull off. The construction costs for the coop and chicken run were enormous and the sinister threat of avian flu hung over the area like a black cloud. It was only through the combined efforts of Matsushita Chickenworks and the City of Edmond that the project would be undertaken, since they would be able to: A) Accept the risk. B) Minimize the risk. C) Transfer the risk. D) Share the risk.
question
A) Liquidated damages.
answer
46) Project penalty clauses that initiate at mutually agreed-on points in the project's development and implementation are: A) Liquidated damages. B) Milestone adjustments. C) Contingency clauses. D) Penalty points.
question
B) A contingency reserve.
answer
47) The firm set aside a little extra money just in case an unforeseen element of cost pushed the project beyond what they had budgeted. This extra money is called: A) A rainy day fund. B) A contingency reserve. C) An escalation clause. D) A sinking fund.
question
C) Fixed price contract.
answer
48) You have agreed to paint your neighbor's house a lovely shade of chartreuse for $1500 and discover much to your dismay that the house has a second floor. Now you're faced with the prospect of buying a ladder or scaffolding or a really long handled brush, not to mention the 15 more gallons of paint that will be needed to cover. You won't get another penny for what will surely be increased efforts since your neighbor transferred risk with a(n): A) Cost-plus contract. B) Contingency reserve. C) Fixed price contract. D) Inflation clause.
question
D) $6,000.
answer
49) The expected cost of an item that is estimated at $5,000 with a task contingency multiplier of 1.2 is: A) $4,167. B) $5,000. C) $5,200. D) $6,000.
question
A) About $15,400.
answer
50) Twenty-thousand dollars was budgeted for the office renovation that had a task contingency multiplier of 1.3. The estimated cost of the task must be: A) About $15,400. B) About $26,000. C) About $22,800. D) About $18,600.
question
B) As the project nears completion, the budgeted reserves tend to decrease.
answer
51) What is the relationship between a project's progress and the level of budget reserves? A) As the project nears completion, the budgeted reserves tend to increase. B) As the project nears completion, the budgeted reserves tend to decrease. C) As the budgeted reserves increase, the project tends to near completion. D) As the budgeted reserves decrease, the project tends to near completion.
question
C) Managerial contingency.
answer
52) The budget safety measures that address higher risks than task contingency are known as: A) CYA factors. B) Buffer stocks. C) Managerial contingency. D) Task offsets.
question
D) An "act of God."
answer
53) A common use of managerial contingency funds would be for: A) Office supplies. B) Management consulting fees. C) A sudden increase in the price of unleaded gasoline. D) An "act of God."
question
A) Mentoring.
answer
54) The act of pairing a junior project team member with a senior manager in order to help the junior team member to learn best practices is known as: A) Mentoring. B) Cross-training. C) Supervising. D) Interning.
question
B) Cross-training program.
answer
55) Each project team member had a backup that could fill in at a moment's notice should another team member fall by the wayside. The project was able to mitigate risks in this fashion thanks to an aggressive: A) Mentoring program. B) Cross-training program. C) Duplication program. D) Featherbedding program.
question
D) PRAM.
answer
56) The European Association for Project Management has developed an integrated program of risk management based on efforts to extend risk management to cover a project's entire life cycle. This program is known as: A) EAPM-RM. B) RMEAPM. C) ERM. D) PRAM.
question
A) Risk management is integrated throughout the project's life cycle.
answer
57) Which of these statements about the project risk analysis and management program is BEST? A) Risk management is integrated throughout the project's life cycle. B) The risk management strategy should be unwavering throughout the entire project life cycle. C) The project manager should choose a small subset of all risk management tools. D) Risk management is best handled using an ad hoc approach.
question
A) Risk management follows a life cycle much as a project follows a life cycle.
answer
58) Which of these statements about the project risk analysis and management program is BEST? A) Risk management follows a life cycle much as a project follows a life cycle. B) The risk management strategy should be unwavering throughout the entire project life cycle. C) If a choice between accepting and transferring risk presents itself, risk should be transferred. D) Risk management is best handled using an ad hoc approach.
question
B) Different risk management strategies should be deployed at various points in the project life cycle.
answer
59) Which of these statements about the project risk analysis and management program is BEST? A) If a choice between accepting and transferring risk presents itself, risk should be transferred. B) Different risk management strategies should be deployed at various points in the project life cycle. C) The project manager should choose a small subset of all risk management tools. D) Risk management is best handled using an ad hoc approach.
question
C) The project manager should choose a small subset of all risk management tools.
answer
60) Which of these statements about the project risk analysis and management program is BEST? A) Risk management is best handled using an ad hoc approach. B) If a choice between accepting and transferring risk presents itself, risk should be transferred. C) The project manager should choose a small subset of all risk management tools. D) Multiple approaches to risk management should be integrated into a coherent, synthesized approach.
question
C) Deliverables.
answer
61) At each phase, the project risk analysis and management program should produce: A) Alternatives. B) A budget. C) Deliverables. D) Meetings.
question
B) Define.
answer
62) One phase of the project risk analysis and management program is concerned more with the project than the management of risk. The latter is facilitated by successful completion of this step, but not the focal point. This phase in the project risk analysis and management program is: A) Estimate. B) Define. C) Focus. D) Manage.
question
B) To make sure the project is well defined, including all deliverables, statement of work, and project scope.
answer
63) The first phase of a comprehensive project risk assessment should be: A) To assess the specific sources of risk at the outset of the project, including the need to fashion appropriate responses. B) To make sure the project is well defined, including all deliverables, statement of work, and project scope. C) To develop reasonable estimates of the impacts on the project of both the identified risks and the proposed solutions. D) To produce a project risk management plan that proactively offers risk mitigation strategies for the project as needed.
question
C) Evaluate
answer
64) The PRAM methodology contains an embedded feedback loop after which step? A) Focus B) Plan C) Evaluate D) Identify
question
D) Manage.
answer
65) The PRAM step that occurs while the project work is being carried out is: A) Ownership. B) Identify. C) Focus. D) Manage.
question
A) structure step
answer
66) The tasks of reviewing and refining the manner in which we have classified risks for the project, determining if there are commonalities across the various risks we have uncovered are performed in the ________ of the project risk analysis and management model. A) structure step B) ownership step C) define step D) plan step
question
B) A clear, unambiguous, shared understanding of all relevant key aspects of the RMP documented, verified, and reported.
answer
67) The deliverable from the focus step of the project risk analysis and management model is: A) A clear, unambiguous, shared understanding of all key aspects of the project documented, verified, and reported. B) A clear, unambiguous, shared understanding of all relevant key aspects of the RMP documented, verified, and reported. C) A clear understanding of the implications of any important simplifying assumptions about relationships between risks, responses and base plan activities. D) Clear ownership and management allocations, effectively and efficiently defined, legally enforceable in practice where appropriate.
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New