Chapter 3: Project Management – Flashcards
Unlock all answers in this set
Unlock answersquestion
            agile methods
answer
        an approach to managing projects that includes an iterative workflow and incremental delivery of software in short iterations
question
            artifact
answer
        a useful object created in short iterations
question
            burndown chart
answer
        a chart that shows the cumulative work remaining in a sprint on a day by day basis
question
            closing process
answer
        formalizing acceptance of the project or
question
            _____ processes include defining and authorizing a project or project phase.
answer
        Initiating
question
            _____ processes include devising and maintaining a workable scheme to ensure that the project addresses the organization's needs.
answer
        Planning
question
            Examples of _____ processes include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements.
answer
        executing
question
            A common _____ process is reporting performance, where project stakeholders can identify any necessary changes that may be required to keep the project on track.
answer
        monitoring and controlling
question
            Administrative activities, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project, are often involved in _____ processes.
answer
        closing
question
            The project time management knowledge area maps to the _____ process group through the activity of schedule contro
answer
        monitoring and controlling
question
            Developing a _____ is a planning process that occurs in the Project Integration Management knowledge area.
answer
        project management plan
question
            The project cost management knowledge area maps to the _____ process group through the activities of estimating costs and budget determination.
answer
        planning
question
            The project stakeholder management knowledge area maps to the _____ process group by identifying stakeholders.
answer
        initiating
question
            _____ is an iterative software development process that focuses on team productivity and delivers software best practices to all team members.
answer
        Rational Unified Process
question
            One of the main outputs of the initiation process is _____.
answer
        developing the project charter
question
            The project management plan is the output of the planning process of project _____.
answer
        integration management
question
            Which of the following is a planning process associated with project scope management?
answer
        Collecting requirements
question
            The _____ provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance.
answer
        work breakdown structure
question
            _____ are an output of the executing process of project integration management.
answer
        Deliverables
question
            Enterprise environmental factors are an output of the executing process of _____.
answer
        project human resource management
question
            The _____ process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end.
answer
        closing
question
            Organizational process assets update is the output of the closing process of _____.
answer
        project integration management
question
            Which of the following is true about the agile method?
answer
        It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.
question
            Which of the following project parameters would be compatible with the use of the agile approach?
answer
        Projects that have more flexible scheduling
question
            project management process groups include:
answer
        initiating processes  planning processes  executing processes  monitoring and controlling processes  closing processes
question
            DMAIC
answer
        (Define, measure, analyze, improve and control) refers to a data-driven improvement cycle used for improving, optimizing and stabilizing business processes and designs