Chapter 3: Project Management – Flashcards
Unlock all answers in this set
Unlock answersquestion
agile methods
answer
an approach to managing projects that includes an iterative workflow and incremental delivery of software in short iterations
question
artifact
answer
a useful object created in short iterations
question
burndown chart
answer
a chart that shows the cumulative work remaining in a sprint on a day by day basis
question
closing process
answer
formalizing acceptance of the project or
question
_____ processes include defining and authorizing a project or project phase.
answer
Initiating
question
_____ processes include devising and maintaining a workable scheme to ensure that the project addresses the organization's needs.
answer
Planning
question
Examples of _____ processes include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements.
answer
executing
question
A common _____ process is reporting performance, where project stakeholders can identify any necessary changes that may be required to keep the project on track.
answer
monitoring and controlling
question
Administrative activities, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project, are often involved in _____ processes.
answer
closing
question
The project time management knowledge area maps to the _____ process group through the activity of schedule contro
answer
monitoring and controlling
question
Developing a _____ is a planning process that occurs in the Project Integration Management knowledge area.
answer
project management plan
question
The project cost management knowledge area maps to the _____ process group through the activities of estimating costs and budget determination.
answer
planning
question
The project stakeholder management knowledge area maps to the _____ process group by identifying stakeholders.
answer
initiating
question
_____ is an iterative software development process that focuses on team productivity and delivers software best practices to all team members.
answer
Rational Unified Process
question
One of the main outputs of the initiation process is _____.
answer
developing the project charter
question
The project management plan is the output of the planning process of project _____.
answer
integration management
question
Which of the following is a planning process associated with project scope management?
answer
Collecting requirements
question
The _____ provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance.
answer
work breakdown structure
question
_____ are an output of the executing process of project integration management.
answer
Deliverables
question
Enterprise environmental factors are an output of the executing process of _____.
answer
project human resource management
question
The _____ process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end.
answer
closing
question
Organizational process assets update is the output of the closing process of _____.
answer
project integration management
question
Which of the following is true about the agile method?
answer
It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.
question
Which of the following project parameters would be compatible with the use of the agile approach?
answer
Projects that have more flexible scheduling
question
project management process groups include:
answer
initiating processes planning processes executing processes monitoring and controlling processes closing processes
question
DMAIC
answer
(Define, measure, analyze, improve and control) refers to a data-driven improvement cycle used for improving, optimizing and stabilizing business processes and designs