Project Management II – Quiz 1 – Flashcards
Unlock all answers in this set
Unlock answersquestion
Actual cost (AC)
answer
The total of direct and indirect costs incurred in accomplishing work on an activity during a given period; formerly called the actual cost of work performed (ACWP).
question
Analogous estimate
answer
A cost-estimating technique that uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project; also called top-down estimate.
question
Baseline
answer
The original project plan plus approved changes.
question
Bottom-up estimate
answer
A cost-estimating technique based on estimating individual work items and summing them to get a project total.
question
Budget at completion (BAC)
answer
The original total budget for a project.
question
Budgetary estimate
answer
A cost estimate used to allocate money into an organization's budget.
question
Cash flow analysis
answer
A method for determining the estimated annual costs and benefits for a project.
question
COCOMO II
answer
A newer, computerized cost-estimating tool based on Barry Boehm's original model that allows one to estimate the cost, effort, and schedule when planning a new software development activity.
question
Computerized tools
answer
Cost-estimating tools that use computer software, such as spreadsheets and project management software.
question
Constructive Cost Model (COCOMO)
answer
A parametric model developed by Barry Boehm for estimating software development costs.
question
Contingency reserves
answer
Dollars included in a cost estimate to allow for future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline.
question
Cost baseline
answer
A time-phased budget that project managers use to measure and monitor cost performance.
question
Cost budgeting
answer
Allocating the overall cost estimate to individual work items to establish a baseline for measuring performance.
question
Cost control
answer
Controlling changes to the project budget.
question
Cost estimating
answer
Developing an approximation or estimate of the costs of the resources needed to complete the project.
question
Cost management plan
answer
A document that describes how cost variances will be managed on the project.
question
Cost performance index (CPI)
answer
The ratio of earned value to actual cost; can be used to estimate the projected cost to complete the project.
question
Cost variance (CV)
answer
The earned value minus the actual cost.
question
Definitive estimate
answer
A cost estimate that provides an accurate estimate of project costs.
question
Direct costs
answer
Costs that can be directly related to producing the products and services of the project.
question
Earned value (EV)
answer
The percentage of work actually completed multiplied by the planned cost; formerly called the budgeted cost of work performed (BCWP).
question
Earned value management (EVM)
answer
A project performance measurement technique that integrates scope, time, and cost data.
question
Estimate at completion (EAC)
answer
An estimate of what it will cost to complete the project based on performance to date.
question
Function points
answer
Technology-independent assessments of the functions involved in developing a system.
question
Indirect costs
answer
Costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.
question
Intangible costs or benefits
answer
Costs or benefits that are difficult to measure in monetary terms.
question
Learning curve theory
answer
A theory that states that when many items are produced repetitively, the unit cost of those items normally decreases in a regular pattern as more units are produced.
question
Life cycle costing
answer
Considers the total cost of ownership, or development plus support costs, for a project.
question
Management reserves
answer
Dollars included in a cost estimate to allow for future situations that are unpredictable (sometimes called unknown unknowns).
question
Overrun
answer
The additional percentage or dollar amount by which actual costs exceed estimates.
question
Parametric modeling
answer
A cost-estimating technique that uses project characteristics (parameters) in a mathematical model to estimate project costs.
question
Planned value (PV)
answer
The portion of the approved total cost estimate planned to be spent on an activity during a given period; formerly called the budgeted cost of work scheduled (BCWS).
question
Profit margin
answer
The ratio between revenues and profits.
question
Profits
answer
Revenues minus expenses.
question
Project cost management
answer
The processes required to ensure that the project is completed within the approved budget.
question
Rate of performance (RP)
answer
The ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity.
question
Reserves
answer
Dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict.
question
Rough order of magnitude (ROM) estimate
answer
A cost estimate prepared very early in the life of a project to provide a rough idea of what a project will cost.
question
Schedule performance index (SPI)
answer
The ratio of earned value to planned value; can be used to estimate the projected time to complete a project.
question
Schedule variance (SV)
answer
The earned value minus the planned value.
question
Source Lines of Code (SLOC)
answer
A human-written line of code that is not a blank line or comment.
question
Sunk cost
answer
Money that has been spent in the past.
question
Tangible costs or benefits
answer
Costs or benefits that can be easily measured in dollars
question
3 Project Management Processes
answer
1 - Estimating the cost 2 - Determining the budget 3 - Controlling costs
question
Why do many projects never finish?
answer
Cost management problems cause many problems to never finish.
question
What are most executives concerned with more than other issues?
answer
profits
question
When do organizations have a history of not spending enough money and what does it impact?
answer
They have a history of not spending enough money in the early phases of projects and it impacts the total cost of ownership.
question
Why is cash flow important?
answer
If top management selects too many projects that have high cash flow needs in the same year, the company will not be able to support all of its projects and maintain profitability.
question
Why is it important to define clearly the year on which the company bases its dollar amounts?
answer
If a company bases all costs on a previous years estimates it would need to account for inflation and other factors when projecting costs and benefits in future-year dollars.
question
3 basic types of estimates
answer
1 - Rough order of magnitude (ROM) 2 - Budgetary estimate 3 - Definitive estimate
question
Earned value management involves calculating which three values for each activity or summary activity from a project's WBS?
answer
1 - Planned Value 2 - Actual Cost 3 - Earned Value
question
_______ is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange.
answer
Cost
question
What is the main goal of project cost management?
answer
to complete a project within an approved budget.
question
If a company loses $5 for every $100 in revenue for a certain product, what is the profit margin for that product?
answer
-5%
question
______ reserves allow for future situations that are unpredictable.
answer
Management
question
You are preparing a cost estimate for a building based on its location, purpose, number of square feet, and other characteristics. What cost estimating technique are you using?
answer
parametric
question
______ involves allocating the project cost estimate to individual work items over time.
answer
Project cost budgeting
question
_____ is a project performance measurement technique that integrates scope, time, and cost data.
answer
Earned value analysis
question
If the actual cost for a WBS item is over $1500 and its earned value was $2000, what is its cost variance, and is it under or over budget?
answer
The cost variance is $500, which is under budget
question
If a project is halfway completed and its schedule performance index is 110 percent and its cost performance index is 95 percent, how is it progressing?
answer
It is ahead of schedule and over budget.
question
The ________ is the additional percentage or dollar amount by which actual costs exceed estimates.
answer
cost overrun
question
Which of the following processes of project cost management involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance?
answer
cost budgeting
question
Which of the following processes of project cost management involves developing an approximation of the costs of the resources needed to complete a project?
answer
cost estimating
question
The main outputs of the ________ process are work performance measurements, budget forecasts, organizational process asset updates, change requests, project management plan updates, and project document updates.
answer
cost control
question
To increase ________, a company can increase revenues, decrease expenses, or try to do both.
answer
profits
question
A company might complete a project to develop and implement a new customer service system in one or two years, but the new system could be in place for ten years. Project managers should create estimates of the costs and benefits of the project for ten years. This is an example of ________.
answer
life cycle costing
question
Avoid ________ when deciding what project to invest in or continue.
answer
sunk costs
question
________ for projects often include items like goodwill, prestige, and general statements of improved productivity that an organization cannot easily translate into dollar amounts.
answer
Intangible costs
question
________ are used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs.
answer
Definitive estimates
question
Which type of estimate is done very early in a project or even before a project is officially started?
answer
rough order of magnitude (ROM) estimate
question
The drawback with ________ is that they are usually time-intensive and therefore expensive to develop.
answer
bottom-up estimates
question
A ________ might provide an estimate of $50 per line of code for a software development project based on the programming language the project is using, the level of expertise of the programmers, the size and complexity of the data involved, and so on.
answer
parametric model
question
Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project?
answer
top-down estimate
question
A(n) ________ is a time-phased budget that project managers use to measure and monitor cost performance.
answer
cost baseline
question
The ________ is an estimate of the value of the physical work actually completed.
answer
earned value (EV)
question
Suppose a project included a summary activity of purchasing and installing a new Web server. Suppose further that, according to the plan, it would take one week and cost a total of $10,000 for the labor hours, hardware, and software involved. The ________ for that activity that week is, therefore, $10,000.
answer
planned value (PV)
question
What is the earned value minus the actual cost?
answer
cost variance (CV)
question
What is the ratio of earned value to planned value and can be used to estimate the projected time to complete the project?
answer
schedule performance index (SPI)
question
Which of the following is the earned value minus the planned value?
answer
schedule variance (SV)
question
What is the ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project?
answer
cost of performance index (CPI)
question
coercive power
answer
using punishment, threats, or other negative approaches to get people to do things they do not want to do
question
deputy project managers
answer
people who fill in for project managers in their absence and assist them as needed similar to the role of a vice president
question
empathic listening
answer
listening with the intent to understand
question
expert power
answer
using one's personal knowledge and expertise to get people to change their behavior
question
extrinsic motivation
answer
causes people to do something fora reword or to avoid a penalty
question
hierarchy of needs
answer
a pyramid structure illustrating maslows theory that peoples behaviors are guided or motivated by a sequence of needs
question
intrinsic motivation
answer
causes people to participate in an activity for their own enjoyment
question
legitimate power
answer
getting people to do things based on a position of authority
question
mirroring
answer
matching certain behaviors of the other person
question
organizational breakdown structure
answer
a specific type of organizational chart that shows which organizational units are responsible for which work items
question
power
answer
getting people to do things they would not otherwise do
question
rapport
answer
a relation of harmony conformity accord or affinity
question
referent power
answer
getting people to do things based on an individual's personal charisma
question
resource histogram
answer
A column chart that shows the number of resources required or assigned to a project over time
question
resource leveling
answer
A technique for resolving resources conflicts by delaying tasks.
question
resource loading
answer
amt of individual resources required during specific time periods.
question
responsibility assignment matrix
answer
matrix that maps the work of the project as described in the WBS to the people responsible for performing the work as described int he organizational breakdown structure
question
reward power
answer
using incentives to induce people to do things
question
subproject managers
answer
people responsible for managing the subprojects that a large project might be broken into
question
synergy
answer
an approach where the whole is greater than the sum of the parts
question
Project Human Resource Management
answer
Making the most effective use of the people involved with a project
question
4 steps for defining and assigning work
answer
1. Finalizing project requirements 2. Defining how the work will be accomplished 3. Breaking down the work into manageable elements 4. Assigning work responsibilities
question
5 dysfunctions of teams
answer
1 - Absence of trust 2 - Fear of conflict 3 - Lack of commitment 4 - Avoidance of accountability 5 - Inattention to results
question
issue log
answer
a tool for managing project teams where the project manager documents, monitors, and tracks issues that need to be resolved in order for the project to run smoothly
question
overallocation
answer
when more resources than are available are assigned to perform work at a given time
question
RACI charts
answer
charts that show Responsibility, Accountability, Consultation, and Informed roles for project stakeholders
question
staffing management plan
answer
a document that describes when and how people will be added to and taken off a project team
question
What do organizations need if they want to be successful at implementing information technology projects?
answer
They need to understand the importance of project human resource management and take actions to make effective use of people.
question
Human resource management includes the following four processes:
answer
1. Developing the human resource plan 2. Acquiring the project team 3. Developing the project team 4. Managing the project team
question
McGregor's Theory X
answer
People who believe in this assume that workers dislike and avoid work if possible, so managers must use coercion, threats, and various control schemes to get workers to make adequate efforts to meet objectives.
question
McGregor's Theory Y
answer
Manager's who believe in this assume that individuals do not inherently dislike work, but consider it as natural as rest or play.
question
Ouchi's Theory Z
answer
Manager's who believe in this assume workers can be trusted to do their jobs to their utmost ability, as long as management can be trusted to support them and look out for their well-being.
question
5 types of power
answer
• Coercive Power • Legitimate Power • Expert Power • Reward Power • Referent Power
question
The human resource plan often includes:
answer
An organizational chart for the project, detailed information on roles and responsibilities, and a staffing management plan.
question
just-in-time training
answer
Training that is given right before it is needed, so that it is fresh in the worker's mind when work begins.
question
What determines the success and failure of organizations and projects?
answer
People
question
5 whys
answer
A technique where you repeatedly ask the question "Why?" (five is a good rule of thumb) to help peel away the layers of symptoms that can lead to the root cause of a problem.
question
Acceptance decisions
answer
Decisions that determine if the products or services produced as art of the project will be accepted or rejected.
question
Appraisal cost
answer
The cost of evaluating processes and their outputs to ensure that a project is error-free or within an acceptable error range
question
Benchmarking
answer
A technique used to generate ideas for quality improvements by comparing specific project practices
question
Capability Maturity Model Integration (CMMI)
answer
A process improvement approach that provides organizations with the essential elements of effective processes
question
Cause-and-effect diagram
answer
Diagram that traces complaints about quality problems back to the responsible production operations to help find the root cause. Also known as fishbone diagram or Ishikawa diagram.
question
Conformance
answer
Delivering products that meet requirements and fitness for use
question
Conformance to requirements
answer
The project processes and products meet written specifications
question
Control chart
answer
A graphic display of data that illustrates the results of a process over time
question
Cost of nonconformance
answer
Taking responsibility for failures or not meeting quality expectations
question
Cost of quality
answer
The cost of conformance plus the cost of nonconformance
question
Defect
answer
Any instance where the product or service fails to meet customer requirements
question
DMAIC (Define, Measure, Analyze, Improve, Control)
answer
A systematic, closed-loop process for continued improvement that is scientific and fact based.
question
Design of experiments
answer
A quality technique that helps identify which variables have the most influence on the overall outcome of a process
question
External failure cost
answer
A cost related to all errors not detected and corrected before delivery to the customer
question
Features
answer
The special characteristics that appeal to users
question
Fishbone diagram
answer
Diagram that traces complaints about quality problems back to the responsible production operations to help find the root cause. Also known as cause-and-effect diagram or Ishikawa diagram
question
Flowchart
answer
Graphic display of the logic and flow of processes that helps you analyze how problems occur and how processes can be improved
question
Fitness for use
answer
A product can be used as it was intended
question
Functionality
answer
The degree to which a system performs its intended function
question
Histogram
answer
A bar graph of a distribution of variables
question
Integration testing
answer
Testing that occurs between unit and system testing to test functionality grouped components to ensure a subset(s) of the entire system works together
question
Internal failure cost
answer
A cost incurred to correct an identified defect before the customer receives the product
question
Ishikawa diagram
answer
Diagram that traces complaints about quality problems back to the responsible production operations to help find the root cause. Also known as cause-and-effect diagram or fishbone diagram
question
ISO 9000
answer
A quality system standard developed by the International Organization for Standardization (ISO) that includes a three-part, continuous cycle of planning, controlling, and documenting quality in an organization
question
Maintainability
answer
The ease of performing maintenance on a product
question
Malcolm Baldrige National Quality Award
answer
An award started in 1987 to recognize companies that have achieved a level of world-class competition through quality management
question
Maturity model
answer
A framework for helping organizations improve their processes and systems
question
Mean
answer
The average value of a population
question
Measurement and test equipment costs
answer
The capital cost of equipment used to perform prevention and appraisal activities
question
Metric
answer
A standard of measurement
question
Normal distribution
answer
A bell-shaped curve that is symmetrical about the mean of the population
question
Pareto analysis
answer
Identifying the vital few contributors that account for most quality problems in a system
question
Pareto chart
answer
Histogram that helps identify and prioritize problem areas
question
Performance
answer
How well a product or service performs the customer's intended use
question
Prevention cost
answer
The cost of planning and executing a project so that it is error-free or within an acceptable error range
question
Process adjustments
answer
Adjustments made to correct or prevent further quality problems based on quality control measurements
question
Project quality management
answer
Ensuring that a project will satisfy the needs for which it was undertaken
question
Quality
answer
The totality of characteristics of an entity that bear on its ability to satisfy stated or implied needs or the degree to which a set of inherent characteristics fulfill requirements
question
Quality assurance
answer
Periodically evaluating overall project performance to ensure that the project will satisfy the relevant quality standards
question
Quality audit
answer
Structured review of specific quality management activities that helps identify lessons learned and can improve performance on current or future projects
question
Quality circles
answer
Groups of nonsupervisors and work leaders in a single company department who volunteer to conduct group studies on how to improve the effectiveness of work in their department
question
Quality control
answer
Monitoring specific project results to ensure that they comply with the relevant quality standards and identifying ways to improve overall quality
question
Quality planning
answer
Identifying which quality standards are relevant to the project and how to satisfy them
question
Reliability
answer
The ability of a product or service to perform as expected under normal conditions
question
Rework
answer
Action taken to bring rejected items into compliance with product requirements or specifications or other stakeholder expectations
question
Robust Design Methods
answer
Methods that focus on eliminating defects by substituting scientific inquiry for trial-and-error methods
question
Run chart
answer
Chart that displays the history and pattern of variation of a process over time
question
Scatter diagram
answer
Diagram that helps to show if there is a relationship between two variables; also called XY charts
question
Seven run rule
answer
If seven data points in a row on a quality control chart are all below the mean, above the mean, or are all increasing or decreasing, then the process needs to be examined for nonrandom problems
question
Six 9s of quality
answer
A measure of quality control equal to 1 fault in 1 million opportunities
question
Six Sigma
answer
A comprehensive and flexible system for achieving, sustaining, and maximizing business success that is uniquely driven by close understanding of customer needs, disciplined use of facts, data, statistical analysis, and diligent attention to managing, improving, and reinventing business processes
question
Software defect
answer
Anything that must be changed before delivery of the program
question
Software Quality Function Deployment (SQFD) model
answer
A maturity model that focuses on defining user requirements and planning software projects
question
Standard deviation
answer
A measure of how much variation exists in a distribution of data
question
Statistical sampling
answer
Choosing part of a population of interest for inspection
question
System outputs
answer
The screens and reports the system generates
question
System testing
answer
Testing the entire system as one entity to ensure that it is working properly
question
Unit test
answer
A test of each individual component (often a program) to ensure that it is as defect-free as possible
question
User acceptance testing
answer
An independent test performed by end users prior to accepting the delivered system
question
Yield
answer
The number of units handled correctly through the development process
question
What is the purpose of project quality management?
answer
to ensure that the project will satisfy the needs for which it was undertaken.
question
Who decides if quality is acceptable?
answer
The customer.
question
3 main processes involved in project quality management
answer
1 - quality planning 2 - quality assurance 3 - quality control
question
Important scope aspects of IT projects that affect quality
answer
Functionality and Features - important to recognize the difference between necessary and optional functionality and features. System outputs - important to define clearly what the screens and reports look like. Can the users easily interpret these outputs? Performance Reliability Maintainability
question
Main outcomes of quality control
answer
Acceptance decisions Rework Process adjustments
question
7 basic tools of quality
answer
1 - cause-and-effect diagrams 2 - control charts 3 - run chart 4 - scatter diagram 5 - histograms 6 - Pareto charts 7 - flow charts
question
stress testing
answer
It involves testing beyond normal operational capacity, often to a breaking point, in order to observe the results.
question
What can assist in improving quality?
answer
Strong leadership, understanding the cost of quality, providing a good workplace to enhance quality, and working toward improving the organization's overall maturity level in software development and project management can all assist in improving quality.
question
What can assist in improving quality?
answer
Strong leadership, understanding the cost of quality, providing a good workplace to enhance quality, and working toward improving the organization's overall maturity level in software development and project management can all assist in improving quality.