Chpater 7 – PMP – Flashcards

Unlock all answers in this set

Unlock answers
question
What is cost management?
answer
Project cost management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget. Project cost management is primarily concerned with the cost of the resources needed to complete project activities.
question
Plan Cost Management Process
answer
is the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. They benefit of this process is that it provides guidance and direction on how the project costs will be managed.
question
7.1 Plan Cost Management
answer
Inputs: Project management plan, Project Charter, EEF, OPA Tools: Expert Judgment, Analytical techniques, Meetings. Outputs: cost management plan **The cost management plan becomes a component of the Project Management Plan **Organizational policies and procedures may influence which financial techniques are employed in these decisions. Techniques may include (but are not limited to): payback period, return on investment, internal rate of return, discounted cash flow, and net present value. **The WBS component used for project cost accounting is called the control account. Each control account is assigned a unique code or account number(s) that links directly to the performing organization's accounting system.
question
Estimate Cost Process
answer
is the process of developing an approximation of the monetary resources needed to complete project activities. The Key benefit of this process is that it determines the amount of cost required to complete project work.
question
7.2 Estimate Costs
answer
Inputs: Cost management plan, human resource management plan, scope baseline, project schedule, Risk register, EEf, OPA Tools: expert judgement, analgous estimating, parametric estimating, bottom-up estimating, three-point estimating, reserve analysis, cost of quality, project management software, vendor bid analysis, group decision-making techniques. Outputs: activity cost estimates, basis of estimates, and project document updates **Costs are estimated for all resources that will be charged to the project. **Three point estimating - Most likely, Optimistic, and Pessimistic --Triangular Distribution and Beta Disctribution
question
What is a cost estimate?
answer
A cost estimate is a quantitative assessment of the likely costs for resources required to complete the activity
question
What is Analogous cost estimating?
answer
Analogous cost estimating is frequently used to estimate a value when there is a limited amount of detailed information about the project, for example, in the early phases of a project. Analogous cost estimating uses historical information and expert judgment
question
What is Bottom-up estimating?
answer
is a method of estimating a component of work. The cost of individual work packages or activities is estimated to the greatest level of specified detail
question
What are Contingency Reserves?
answer
are the budget within the cost baseline that is allocated for identified risks which are accepted. Contingency reserves are often viewed as the part of the budget intended to address the "known-unknowns" that can affect the project (part or reserve analysis).
question
Determine Budget Process
answer
is the process of aggregating these estimated costs of individual activities or work packages to establish an authorized cost baseline. The key benefit of this process is that it determines the cost baselines against which project performance can be monitored and controlled.
question
7.3 Determine Budget
answer
Inputs: Cost management plan, scope baseline, activity cost estimates, basis of estimates, project schedule, resource calendars, risk register, agreements, and OPA Tools: Cost aggregation, reserve analysis, expert judgment, historical relationships, funding limit reconciliation Outputs: Cost baseline, project funding requirements, project document updates
question
Project Budget Characteristics
answer
**A project budget includes all of the funds authorized to execute the project. The cost baseline is the approved version of the time-phased project budget, but excludes management reserves. **The cost baseline is typically displayed in an "S" curve
question
Control Code Process
answer
is the process of monitoring the status of the project update to the project costs and managing changes to the cost baseline. The key benefit of this process is that it provides the means to recognize variance from the plan in order to take corrective action and minimize risk
question
7.4 - Control Costs
answer
Inputs: project management plan, project funding requirements, work performance data, organizational process assets Tools: Earned value management, forecasting, to-complete performance index, performance reviews, project management software, reserve analysis. Outputs: Work performance information, cost forecasts, change requests, Project Management plan updates, project documents updates, organizational process assets updates
question
Control Cost Characteristics/facts
answer
**Much of the effort of cost control involves analyzing the relationship between the consumption of project funds to the physical work being accomplished for such expenditures. **Work performance data - includes information about project progress, such as which activities have started, their progress, and which deliverables have finished.
question
EAC
answer
estimate cost at completion
question
Human resource management plan
answer
provides project staffing attributes, personnel rates, and related rewards/recognition, which are necessary components for developing the project cost estimates
question
Direct Costs
answer
costs associated or linked directly to a project
question
Indirect Costs
answer
are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated equitably over multiple projects by some approved and documented procedure
question
Management Reserves
answer
Is an amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. Management reserves are intended to address the "unknown-knowns" that can affect a project. Management reserve is NOT part of the cost baseline
question
Activity Cost Estimates
answer
are quantitative assessments of the probable costs required to complete project work. Cost estimates can be presented in summary form or detail. Costs are estimated for all resources that are applied to the activity cost baseline.
question
EVM
answer
Earned Value management, is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. EVM develops and monitors 3 key dimensions for each work package and control account which are: planned value, earned value, and actual cost.
question
Planned Value (PV)
answer
is the authorized budget assigned to scheduled work. It is the authorized budget planned for the work to be accomplished for an activity or work breakdown structure component, not including management reserve.
question
Earned Value (EV)
answer
Earned value (EV) is a measure of work performed expressed in terms of the budget authorized for the work. The EV being measured cannot be greater than the authorized PV. EV is often used to calculate the percent complete of a project
question
Actual Cost (AC)
answer
is the realized cost incurred for the work performed on an activity during a specific time period. It is the total cost incurred in accomplishing the work that the EV measured. The AC will have no upper limit; whatever is spent to achieve the EV will be measured.
question
Schedule Variance
answer
Schedule Variance (SV) is a measure of schedule performance expressed as the difference between the earned value and the planned value. It is the amount by which the project is ahead or behind the planned delivery date, at a given point in time. The EVM schedule variance is a useful metric in that it can indicate when a project is falling behind or is ahead of its baseline. SV=EV-PV
question
Cost Variance
answer
is the amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and actual cost. It is a measure of cost performance on a project. It is the measure of cost performance on a project. The cost variance at the end of the project will be the difference between the budget at completion minus the actual amount spent. CV = EV-AC
question
Schedule Performance Index (SPI)
answer
(SPI) The schedule performance index (SPI) is a measure of schedule efficiency expressed as the ratio of earned value to planned value. It measures how efficiently the project team is using time. **An SPI > 1.0 indicates less work was completed than was planned. **AN SPI < 1.0 indicates that more work was completed than was planned for. **SPI = EV/PV
question
Cost Performance Index
answer
the cost performance index (CPI) is a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost. It is considered the most critical EVM metric and measures the cost efficiency for the work completed. **CPI > 1.0 indicates a cost overrun for work completed **CPI < 1.0 indicates a cost overrun of performance to date **CPI = EV/AC
question
ETC
answer
estimate to complete
question
EAC
answer
estimate at completion
question
BAC
answer
budget at completion
question
TCPI
answer
is the calculated cost performance index that is achieve on the remaining work to meet a specified management goal, such as the BAC or the EAC. If it becomes obvious that the BAC is no longer viable, the project manager should consider the forecasted EAC. Once approved, the EAC may replace the BAC in the TCPI calculation. **EAC: (BAC-EV)/(EAC- AC)
question
VAC
answer
Variance at completion **VAC = BAC - EAC
question
Time Value of Money Net Present Value, NPV Concepts?
answer
PV, present value FV, future value NPV, net present value IRR, internal rate of return Payback period Break even analysis ROI, return on investment
question
Depreciation Concepts?
answer
Purpose Straight line Accelerated
question
Types of Costs
answer
Direct vs indirect Fixed vs variable Sunk cost Opportunity cost
question
What is rough order of magnitude (ROM)?
answer
an estimate of costs and time provided in the early stages of a project when its scope and requirements has not been fully defined. An ROM is used to reduce the uncertainty of cost outcomes for both parties when project details have yet to be defined. It is the most difficult to estimate and made during the initiating process.
question
Hierarchy of Costs
answer
Cost Budget Management Reserves Cost baseline Contingency reserves Project estimates Control account estimates work package estimates activity estimates
question
Contingency Reserves
answer
the cost impacts of remaining risk. The known-unknowns
question
Management reserves
answer
extra fund to cover unforeseen risk or changes to the project. The unknown-unknowns. They are an amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within scope of the project.
question
When is analogous estimating most reliable?
answer
Analogous estimating is most reliable when the previous projects are similar in fact and not just in appearance, and the project team members preparing the estimates have the needed expertise
question
When is analogous estimating most likely used?
answer
Analogous estimating is frequently used to estimate value when there is limited amount of detailed information about the project, for example, in the early phases of a project.
question
What are the two common formulas used to perform three-point estimating?
answer
Triangular Distribution and Beta Distribution
question
Difference between project budget and cost baseline
answer
A project budget includes all the funds authorized to execute the project. The cost baseline is the approved version of the time-phased budget, but excludes management reserves.
question
What is reserve analysis and what can it establish?
answer
Budget reserve analysis can establish contingency reserves and management reserves for the project.
question
Forecasting..
answer
EAC is always used as a form of forcasting - trying to figure out how much the rest of the project is going to cost you based on the data you have thus far
question
what two EVM concepts are used to measure efficiency?
answer
SPI CPI
question
What is NPV
answer
Net present value - takes into account for all future cash flows. Discounts both income and outlays. NPV > 0 is a GOOD investment and NPV < ) is a BAD investment
question
Payback period
answer
the number of years until costs are covered. Dosent usually take "Time value of Money" into account ( as does NPV and IRR)
question
IRR
answer
Internal Rate of Return - Average payback rate where costs = benefits. Discount rate where NPV = 0.
question
Break Even Analysis
answer
The level of output when costs = benefits. It is usually reported in production units.
question
ROI
answer
Return on Investment - popular accounting tool for identifying the value of an investment. Calculates the percentage paid back to the organization for the money spent. ** (gain from Inv. - Cost of Inv.)/ Cost of inv
question
There are two types of depreciation..
answer
Straight-line and accelerated
question
Straight line
answer
uses initial value, useful life (years), and salvage value **Yearly depreciation = (initial - salvage)/ years
question
Accelerated
answer
allows for higher depreciation at the beginning of an assets life - sum of the years digits -double declining balance - MACRS
question
Accuracy of estimate methods?
answer
Rough order magnitude (ROM) - during initiation Definitive Estimate - done at end of planning.
question
Cost baseline
answer
Expected actual cost of activities plus contingency reserves = cost baseline
question
is the management reserve included in the cost baseline?
answer
NO!!!!! ya heard?!
question
What is a reserve?
answer
a provision in the project management plan to mitigate cost and/or schedule risk
question
contingency reserve
answer
budget within the cost baseline that is allocated for identified risks that are accepted and for which contingent or mitigating responses are developed. - known-unknowns - included in budget - included in cost baseline - not part of earned value calculations
question
The BAC is also known as
answer
PMB - Performance Measurement Baseline
question
Does BAC change
answer
BAC does not EVER change unless the project is rebaselined.
question
Can Forecasting be used for both cost and schedule?
answer
NO! You idiot!!! Forecasts only COSTS - not schedule
question
Forecasting requires computation of what?
answer
ETC - Estimate to Complete & EAC - Estimate at Completion
question
ETC definition
answer
the amount of money needed to complete the project from this point, ignoring all SUNK costs **ETC = EAC - AC
question
EAC definition
answer
the forecasted total cost of the project. Use BAC as a comparison always. **EAC = ETC + AC
question
There are how three way to calculate EAC
answer
atypical variances EAC= AC+BAC-EV typical variances EAC=BAC/CPI Bottom-up (new estimate) EAC=AC+ revised EAC
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New