Chapter 3- Project Management (T/F) – Flashcards

Unlock all answers in this set

Unlock answers
question
The ES of an activity that has only one predecessor is simply the EF of that predecessor
answer
True
question
One phase of a large project is scheduling
answer
True
question
A project organization works best for an organization when the project resides in only one of its functional areas
answer
False
question
By their very nature, projects have a limited lifetime, and that sets project management apart from the management of more traditional activities
answer
True
question
One responsibility of a project manager is to make sure that the project meets its quality goals
answer
True
question
Work Breakdown Structure is a useful tool in project management because it addresses the timing of individual work elements
answer
False
question
Project managers have their own code of ethics, established by the Project Management Institute
answer
True
question
Ethical issues which can arise in projects include bid rigging, bribery, and "low balling"
answer
True
question
Gantt charts give a timeline for each of a projects activities, but do not adequately show the interrelationships of activities
answer
True
question
PERT, but not CPM, has the ability to consider the precedence relationships in a project
answer
False
question
The shortest of all paths through the network is the critical path
answer
False
question
The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates
answer
False
question
Slack is the amount of time an activity can be delayed without delaying the entire project
answer
True
question
Every network has at least one critical path
answer
True
question
The critical path can be determined by use of either the "forward pass" or the "backward pass"
answer
False
question
The standard deviation of project duration is the average of the standard deviation of all activities on the critical path
answer
False
question
In PERT analysis, the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time
answer
True
question
Shortening the project duration by deleting unnecessary activities is called "project crashing"
answer
False
question
In project management, crashing an activity must consider the impact on all paths in the network
answer
True