FIN 3113 Chapter 9 – Flashcards
Unlock all answers in this set
Unlock answersquestion
In capital budgeting, the net ______ determines the value of a project to the company.
answer
Present Value
question
If NPV is positive, the project should be ______.
answer
Accepted
question
If NPV is negative, the project should be _______.
answer
Rejected
question
3 attributes of NPV are that it:
answer
uses all the cash flows of a project, uses cash flows, & discounts the cash flows properly.
question
Length of time until the sum of the discounted cash flows is equal to the initial investment.
answer
Discounted payback period
question
Capital budgeting method allows lower management to make smaller, everyday financial decisions effectively.
answer
Payback method
question
Weaknesses of the payback method
answer
cash flows received after the payback period are ignored, time value of money principles are ignore, cutoff date is arbitrary
question
Capital budgeting decision method finds the present value of each cash flow before calculating a payback period
answer
Discounted payback period
question
Discounted payback rule has an objective benchmark to use in decision making. True/False
answer
False
question
Payback period tells the time it takes to break even in an _________ sense.
answer
Accounting
question
Discounted payback period tells the time it takes to break even in an _______or financial sense.
answer
Economic
question
When cash flows are conventional, NPV is ______.
answer
Positive for discount rates below the IRR, equal to zero when the discount rate equals the IRR, and negative for discount rates above the IRR.
question
The IRR rule can lead to bad decisions when _____ or ______.
answer
Projects are mutually exclusive, cash flows are not conventional.
question
The point at which the NPV profile crosses the horizontal axis is the:
answer
Internal Rate of Return
question
Mutually exclusive investment decisions
answer
a situation in which taking one investment prevents the taking of another.
question
Mutually exclusive investments
answer
2 different choices for the assembly lines that will make the same product, & a restaurant or gas station on the same piece of land.
question
Weaknesses of Discounted payback period
answer
Arbitrary cutoff date, exclusion of some cash flows, and loss of simplicity as compared to the payback method
question
When cash flows are conventional, NPV is ________ if the discount rate is above the IRR.
answer
Negative
question
The present value of all cash flows after the initial investment is divided by the _____to calculate the profitability index.
answer
initial investment
question
Some projects, such as mines, have cash outflows followed by cash inflows, which are then followed by cash outflows, giving the project multiple rates of return.
answer
True
question
If a project has multiple internal rates of return, which of the following methods should be used?
answer
NPV & MIRR
question
According to the basic IRR rule, we should____
answer
reject a project if the IRR is less than the required return.
question
The crossover rate is the rate at which the NPV's of 2 projects are equal.
answer
True
question
IRR is 14%, if required return is 14%, the project's NPV is:
answer
Zero
question
Budgeting methods are most used by the firms in the US and Canada
answer
IRR & NPV
question
Point at which the NPV profile crosses the vertical axis is the:
answer
Sum of the cash flows of the project.
question
Investing more money in a project is a guarantee of greater profits.
answer
False
question
NPV accounts for the size of the project and eliminates the effects of _______
answer
Scale
question
Decision making process for accepting and rejecting projects
answer
Capital budgeting
question
An ______ project does not rely on the acceptance or rejection of another project
answer
Independent
question
How does the timing and the size of cash flows affect the payback method?
answer
An increase in the size of the first cash inflow will decrease the payback method, all else held constant
question
IRR is the discount rate that makes the NPV of a project equal to _______.
answer
zero
question
Most important alternative to NPV is the ____ method.
answer
IRR
question
Point at which the NPV profile crosses the horizontal axis is the:
answer
IRR
question
IRR continues to be very popular in practice, partly because:
answer
gives a rate of return rather than a dollar value
question
Amount of time needed for the cash flows from an investment to pay for its initial cost is the:
answer
payback period
question
Profitability index is calculated by dividing the PV of the ______ CF by initial investment.
answer
Future
question
Two challenges with the IRR approach when comparing 2 mutually exclusive projects are scale and cash flow timing.
answer
True
question
The payback period rule ____ a project if it has a payback period that is less than or equal to a particular cutoff date.
answer
Suggests accepting