Which of the following statements regarding CPM networks is true?
answer
A. The late start of an activity is its late finish plus its duration
B. There can be multiple critical paths on the same project, all with different durations
C. If a specific project has multiple critical paths, all of them will have the same duration
D. The early finish of an activity is the latest early start of all preceding activities
E. None of the above are true
Correct Answer: C
question
Among the following, critical path and slack time analysis, MOST help
answer
A. pinpoint activities that need to be closely watched
B. point out who is responsible for various activities
C. managers define the project activities
D. highlight relationships among project activities
Correct Answer: A
question
With respect to PERT and CPM, slack
answer
is the amount of time a task may be delayed without changing the overall project completion time
question
A project organization:
answer
is effective for companies with multiple large projects
question
Which of the following activities does NOT belong to the controlling phase of project management
answer
A. shift resources
B. define the project
C. revise plans
D. monitor resources, costs, quality, and budgets
Correct Answer: B
question
Which of the following is a direct responsibility of the project manager?
answer
A. drawing the network diagram
B. calculating completion probabilities for all tasks in the project
C. performing all of the activities in the project
D. making sure that the people assigned to the project receive the motivation, direction, and information to do their jobs
Correct Answer: D
question
Which of the following steps is NOT a basic step followed by PERT and CPM?
answer
A. compute the critical path
B. draw the network connecting all the activities
C. identify and eliminate non-critical activities
D. define the project
Correct Answer: C
question
Which of the following represents the FIRST step to crash a project?
answer
A. compute the crash cost per week for each activity in the network
B. select the best activity to be crashed and crash it by one period
C. find the critical path(s) in the project network
D. update all activity times
Correct Answer: A
question
Gantt charts are:
answer
planning charts used to schedule resources and allocate time
question
If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost ... cost per period?
answer
$400