PMP 5th Edition – Definition – Flashcards
Unlock all answers in this set
Unlock answersquestion
Acceptance Criteria
answer
A set of conditions that is required to be met before deliverables are accepted.
question
Accepted Deliverables
answer
Products, results, or capabitlities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria.
question
Accuracy
answer
Within the quality management system, -------- is an assessment of correctness.
question
Acquire Project Team
answer
The process of confirming human resource availability and obtaining the team necessary to complete project activities.
question
Acquisition
answer
Obtaining human and material resources necessary to perform project activities. -------- implies a cost of resources, and is not necessarily financial.
question
Activity
answer
A distinct, scheduled portion of work performed during the course of a project.
question
Activity Attributes
answer
Multiples attributes associated with each schedule activity that can be included within the activity list. -------- -------- include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
question
Activity Code
answer
One or more numerical or text values that identify characteristics of the work or in some way categorize the schedule activity that allows filtering and ordering of activities within reports.
question
Activity Cost Estimates
answer
The projected cost of the schedule activity that incldes the cost for all resources required to perform and complete the activity, including all cost types and cost components.
question
Activity Duration
answer
The time in calendar units beween the start and finish of a schedule activity. See also duration.
question
Activity Duration Extimate
answer
A quantitative assessment of the likely amount or outcome for the duration of an activity.
question
Activity identifier
answer
A sehort, unique numeric or text identification assigned to each schedule activity to differenciate that project activity from other activities. Typcialla unique within any one project schedule network diagram.
question
Activity List
answer
A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
question
Activity Network Diagrams
answer
See project schedule network diagram.
question
Activity-on-Node (AON)
answer
A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
question
Activity Resource Requirements
answer
The types and quantities of resources required for each activiy in a work package.
question
Actual Cost (AC)
answer
The realized cost incurred for the work performed on an activiy during a specific time period.
question
Actual Duration
answer
The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete.
question
Adaptive Life Cycle
answer
A project life cycle, also known as change-driven or agile methods, that is intended to facilitate change and require a high degree of ongoing stakeholder involvement. -------- -------- -------- are also iteratives an incremental, but differ in that iterations are very rapid (usually2-4 weeks in length) and are fixed in time and resources.
question
Additional Quality Planning Tools
answer
A set of tools used to define the quality requirements and to plan effective quality management activities. They include, but are not limited to: brainstorming, force field analysis, nominal group techniques and quality management and control tools.
question
Adjusting Leads and Lags
answer
A technique used to find ways to bring project activities that are behind into alignment with plan during project execution.
question
Advertising
answer
The process of calling public attention to a project or effort.
question
Affininity Diagram
answer
A group creativity technique that allows large numbers of ideas to be classified into groups for review and analysis.
question
Agreements
answer
Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum of understanding (MOU) letters of agreement, verbal agreements, emails, etc.
question
Alternative Analysis
answer
A technique used to evaluate identified options in order to select wich options or approaches to use to executeand perform the work of the project.
question
Alternatives Generation
answer
A technique used to develop as many potential options as possible in order to identify different approaches to execute and perform the work of the project.
question
Analogous Estimating
answer
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
question
Analytical Techniques
answer
Various techniques used to evaluate, analyze, or forecast potential outcomes bases on possible variations of project or environmental variables and their relationships with other variables.
question
Application Area
answer
A category of projects that have common components significant in such projects, but are not needed or present in all projects. -------- --------are usally defined in terms of either the product (i.e., by similar technologies or production methods) or the type of customer (i.e., internal versus external, government versus commercial) or industry sector (i.e., utilities, automotive, aerospace, information technologies, etc.). -------- -------- can overlap.
question
Applying Leads and Lags
answer
A technique that is used to adjust the amount of time betwenn predecessor and successor activities.
question
Apportioned Effort
answer
An activity where effort is allotted proportionaltely across certain discrete efforts and not divisible into discrete efforts. [Note: -------- -------- is one of three earned value management (EVm) types of activities used to measure work performance.]
question
Approved Change Request
answer
A -------- -------- that has been processed through the integrated change control process and approved.
question
Approved Change Requests Review
answer
A review of the -------- -------- to verify that these were implemented as approved.
question
Assumption
answer
A factor in the planning process that is considered to be true, real, or certain, without proff or demonstration.
question
Assumptions Analysis
answer
A technique that explores the accuracy of assumptions and identifies risks to the project from inaccuracy, inconsistency, or incompleteness of assumptions.
question
Attribute Sampling
answer
Method of measuring quality that consists of noting the precense (or absence) of some characteristic (attribute) in each of the units under consideration. After each unit is inspected, the decision is made to accept a lot, reject it, or inspect another unit.
question
Authority
answer
The right to apply project resources, expend funds, make decisions, or give approvals.
question
Backlog
answer
A listing of product requirements and deliverables to be completed, written as stories, and prioritized by the business to manage and organize the project's work.
question
Backward Pass
answer
A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
question
Bar Chart
answer
A graphic display of schedule-related information. In the typical -------- --------, schedule activities or work breakdown structure components are listed down the left side of the chart, dates are shown accross the top, and activity durations are shown as date-placed horizontal bars.
question
Baseline
answer
The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
question
Basis of Estimates
answer
Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.
question
Benchmarking
answer
-------- is the comparison of actual or planned practices, such as processes and operations, to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.
question
Bidder Conference
answer
The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement.
question
Bottom-Up Estimating
answer
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)
question
Brainstorming
answer
A general data gathering and creativity technique that can be used to identify risks, ideas, or solutions to issues by using a group of team members or subject matter experts.
question
Budget
answer
The approved estimate for the project or any work breakdown structure component or any schedule activity.
question
Budget at Completion (BAC)
answer
The sum of all budgets established for the work to be performed.
question
Business Case
answer
A documented economic feasability study used to establish validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.
question
Business Value
answer
A concept that is unique to each organization and includes tangible and intangible elements. Through the effective use of project, program, and portfolio management disciplines, oganizations will possess the ability to employ reliable, established processes to meet enterprise objectives
question
Buyer
answer
The acquirer of products, Services, or results for an organization.
question
Cause and Effect Diagram
answer
A decomposition technique that helps trace an undesirable effect back to ist root cause.
question
Central Tendency
answer
A property of the central Limit Theorem predicting that the data observations in a distrivution will tend to Group around a central Location. The three typical measures of -------- -------- are the mean, median and mode.
question
Change Control
answer
A process whereby modifications to documents, deliverables, or baselines associated with the Project are identified, documented, approved, or rejected.
question
Change Control Board (CCB)
answer
A formally chartered Group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the Project, and for recording and communicating such decisions.
question
Change Control System
answer
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
question
Change Control Tools
answer
Manual or automated tools to assist with change and/or configuration management. At a minimum, the tools should support the activities of the CCB.
question
Change Log
answer
A comprehensice list of changes made during the project. This typically includes dates of the change and impacts in term of time, cost, and risks.
question
Change Request
answer
A formal proposal to modify any document, deliverable, or baseline.
question
Checklist Analysis
answer
A technique for systematically reviewing materials using a list for accuracy and completeness.
question
Checksheets
answer
A tally sheet that can be used as a checklist when gathering data.
question
Claim
answer
A request, demand, or assertion of rights by a seller against buyer, or vice versa, for consideration, compensation, or payment under the terms of a legally binding contract, such as for a disputed Change.
question
Claims Administration
answer
The process of processing, adjudicating, and communicating contract claims.
question
Close Procurements
answer
The process of completing each project procurement.
question
Close Project or Phase
answer
The process of finalizing all activities across all of the Project Management Process Groups to formally complete a project or phase.
question
Closed Procurements
answer
Project contracts or other procurement agreement that have been formally acknowleged by the proper authorizing agent as being finalized and signed off.
question
Closing Process Group
answer
Those processes performed to finallize all activities across all Process Groups to formally close a project or phase.
question
Code of Accounts
answer
A numbering System used to uniquely identify each component of the work breakdown structure (WBS).
question
Collect Requirements
answer
The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.
question
Colocation
answer
An organizational placement strategy where the project team members are physically located close to one another in order to improve communication, workuing relationships, and productivity.
question
Communication Constraints
answer
Restrictions on the content, timing, audience, or individual who will deliver a communication usually stemming from specific legislation, technology, or organizational policies.
question
Communication Methods
answer
A systematic procedure, technique, or process used to transfer Information among project stakeholders.
question
Communication Models
answer
A description, analogy or schematic used to represent how the communication process will be performed for the project.
question
Communication Requirements Analysis
answer
An analytical technique to determine the Information needs of the project stakeholders through interviews, workshops, study of lessons learned from previous projects, etc...
question
Communication Technology
answer
Specific tools, systems, computer programs, etc..., used to transfer Information among project stakeholders.
question
Communications Management Plan
answer
A component of the project, program, or portfolio management plan that describes how, when, and by whom Information about the project will be administered and dissemninated.
question
Compliance
answer
A general concept of conforming to a rule, standard, law, or requirement such that the assessment of compliance results in a binomial result stated as "compliant" or "noncompliant".
question
Conduct Procurements
answer
The process of obtaining seller Responses, selcting a seller, and awarding a contract.
question
Configuration Management System
answer
A subsystem of the overall project management system. It is a collection of formal documented procedures used to apply technical and administrative direction and surveillance to: identify and document the functional and physical characteristics of a product, result, service, or component; control any changes to such characteristics; record and repoort each change and ist implementation status; and Support Audit of the products, result, or components to verfiy conformance to requirements. It includes the documentation, tracking systems, and defined approval Levels necessary for authorizing and controlling changes.
question
Conflict Management
answer
Handling, Controlling, and guiding a conflictual Situation to achieve a resolution.
question
Conformance
answer
Within the quality management system, conformance is a general concept of delivering results that fall within the Limits that define acceptable variation for a quality requirements.
question
Conformance Work
answer
In the cost of Quality Framework, conformance work is done to compensate for imperfcetions that prevent organizations form completing planned activities correctly as essential first-time work. -------- -------- consists of Actions that are related to prevention and inspection.
question
Constraint
answer
A limiting factor that effects the execution of a project, program, portfolio, or process.
question
Context Diagrams
answer
A visual depiction of the product scope showing a business system (process, equipment, computer system, etc.), and how people and other systems (actors) interact with it.
question
Contingency
answer
An event or occurance that could affect the execution of the project that may be acconted for with a reserve.
question
Contingency Reserve
answer
Budget within the cost baseline or performance measurement baseline that is allocated for identified risks that are accepted and for wich contingent or mitigating responses are developed.
question
Contingent Response Strategies
answer
Responses provided which may be used in the event that a specific trigger occurs.
question
Contract
answer
A contract is a mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.
question
Contract Change Control System
answer
The system used to collect, track, adjudicate, and communicate changes to a contract.
question
Control
answer
Comparing actual performance with planned performance, analyzing variances, assessing trends to aeffect process improvements, evaluating possible alternatives, and recommending appropriate corrective action is needed.
question
Control Account
answer
A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.
question
Control Chart
answer
A graphic display of process data over time and against established control limits, which has a centerline that assists in detecting a trend of plotted values toward either control limit.
question
Control Communications
answer
The process of monitoring and -------- -------- throughout the entire project life cycle to ensure the information needs of the project stakeholders are met.
question
Control Costs
answer
The process of monitoring the status of the project to update the project costs and managing changes to the baseline.
question
Control Limits
answer
The area composed of three standard deviations on either side of the centerline or mean of a normal distribution of data plotted on a control chart, which reflects the expected variation in the data.
question
Control Procurements
answer
The process of managing procurement realtionships, monitoring contract performance, and making changes and corrections as appropriate.
question
Control Quality
answer
The process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.
question
Control Risks
answer
The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.
question
Control Schedule
answer
The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
question
Control Scope
answer
The process of monitoring the status of the project and product scope and managing changes to the scope baseline.
question
Control Stakeholder Engagement
answer
The process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders.
question
Corrective Action
answer
An intentional activity that realigns the performance of the project work with the project management plan.
question
Cost Aggregation
answer
Summing the lower-level cost estimates associated with the various work packages for a given level within the project^s WBS or for a given cost control account.
question
Cost Baseline
answer
The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
question
Cost Management Plan
answer
A component of a project or program management plan that describes how costs will be pleanned, structured, and controlled.
question
Cost of Quality
answer
A method of determining the costs incurred to ensure quality. Prevention and appraisal costs (cost of conformance) include costs for quality planning, quality control (QC), and quality assurance to ensure compliance to requirements (i.e., training, QC systems, etc.). Failure costs (cost of nonconformance) incude costs to rework products, components, or processes that are non-compliant, costs of warranty work and waste, and loss of reputation.
question
Cost Performanc Index (CPI)
answer
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
question
Cost Plus Award Fee Contracts (CPAF)
answer
A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit.
question
Cost Plus Fixed Fee Contract (CPFF)
answer
A type of cost-reimbursable contract where the buyer reimburses the selle for the seller's allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).
question
Cost Plus Incentive Fee Contract (CPIF)
answer
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller's alowqable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.
question
Cost Variance (CV)
answer
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
question
Cost-Benefit Analysis
answer
A financial analysios tool used to determine the benefits provided by a project against its costs.
question
Cost-Reimbursable Contract
answer
A type of contract involving payment to the seller for the seller's actual costs, plus a fee typically representing seller's profit. Cost-reimbursable contracts often include incetive clauses where, if the seller meets or exceeds selected project objectives, such as schedule targets or total cost, the the seller receives from the buyer an incetive or bonus payment.
question
Crashing
answer
A technique used to shorten the schedule duration for the least incremental cost by adding resources.
question
Create WBS
answer
The process of subdividing project deliverables and project work into smaller, more manageable components.
question
Criteria
answer
Standards, rules, or tests on which a judgment or decision can be based or by which a product, service, result, or process can be evaluated.
question
Critical Chain Method
answer
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
question
Critical Path
answer
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.
question
Critical Path Activity
answer
Any activity on the critical path in a project schedule.
question
Customers
answer
-------- is the person(s) or organization(s) that will pay for the project's product, service, or result. -------- can be internal or external to the performing organization.
question
Customer Satisfaction
answer
Within the quality management system, a state of fullfillment in which the needs of a customer are met or exceeded for the customer's expected experiences as assessed by the customer at the moment of evaluation.
question
Data Date
answer
A point in time when the status of the project is recorded.
question
Data Gathering and Representation Techniques
answer
Techniques used to collect, organize, and present data and information.
question
Decision Tree Analysis
answer
A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
question
Decomposition
answer
A technique used for dividingand subdividing the project scope and project deliverables into smaller, more manageable parts.
question
Defect
answer
An imperfection or deficiency in a project component where that component does not meet its requirements or specifications and needs to be either repaired or replaced.
question
Defect Repair
answer
An intentional activity to modify a nonconforming product or product component.
question
Define Activities
answer
The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
question
Define Scope
answer
The process of developing a detailed description of the project and product.
question
Deliverable
answer
Any unique and verificable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.
question
Delphi Technique
answer
An information gathering technique used as a way to reach a consensus of experts on a subject. Experts on the subject participate in this technique anonymously. A facilitator uses a questionnaire to solicit ideas about the important project points relared to the subject. The responses are summarized and are then recirculated to the experts for further comment. Consensus may be reached in a few rounds of this process. The -------- -------- helps reduce bias in the data and keeps any one person from having undue influence on the outcome.
question
Dependency Determination
answer
A technique used to identify the type of dependency that is used to create the logical relationships between predecessor and successor activities.
question
Design of Experiments
answer
A statistical method for identifying which factors may influence specific variables of a product or process under development or in production.
question
Determine Budget
answer
The process of aggregatingthe estimated costsof individual activities or work packages to establish an authorized cost baseline.
question
Develop Project Charter
answer
The processof developing a document that formallyauthorizes the existence of a project and provides the project manager with theauthority to apply organizational resources to project activties.
question
Develop Project Management Plan
answer
The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensice project management plan.
question
Develop Project Team
answer
The process of improving competencies, team member interaction, and overall team environment to enhance project performance.
question
Develop Schedule
answer
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
question
Diagramming Techniques
answer
Approaches to presenting information with logical linkages that aid in understanding.
question
Dictatorship
answer
A group decision-making technique in which one individual males the decision for the group.
question
Direct and Manage Project Work
answer
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project's objectives.
question
Discrete Effort
answer
An activity that can be planned and measured and that yields a specific output. [Note: Discrete effort is one of three earned value management (EVM) types of activities used to measure work performance.]
question
Discretionary Dependency
answer
A relationship that is established base on knowledge of best practices within a particual application area or an aspect of the project where a specific sequence is desired.
question
Document Analysis
answer
An elicitation technique that analyzes existing documentation and identifies information relevant to the requirements.
question
Documentation Reviews
answer
The process of gathering a corpus of information and reviewing it to determine accuracy and completeness.
question
Duration (DU or DUR)
answer
The total number of work periods (not including holidays or other nonworking periods) required to complete a schedule activity or work breakdown structure component. Usually expressed asworkdays or workweeks. Sometimes incorrectly equated with elapsed time. Contrast with effort.
question
Early Finish Date (EF)
answer
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints.
question
Early Start Date (ES)
answer
In the cirtical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule newtork logic, the data date and any schedule constraints.
question
Earned Value (EV)
answer
The measure of work performed expressed in terms of the budget authorized for that work.
question
Earned Value Management
answer
A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
question
Effort
answer
The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks.
question
Emotional Intelligence
answer
The capability to identify, assess, and manage the personal emotions of oneself and other people, as wellas the collective emotions of groups of people.
question
Enteprise Environmental Factors
answer
Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio.
question
Estimate
answer
A quantitative assessment of the likely amount or outcome. Usually applied to project costs, resources, effort, and durations and is usually preceded by a modifier(i.e., preliminary, conceptual, feasibility, order-of-mangnitude, definitive). It should always include some indication of accuracy (e.g., +/- x percent).
question
Estimate Activity Durations
answer
The process of estimating the number of work periods needed to complete individual activities with estimated resources.
question
Estimate Activity Resources
answer
The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
question
Estimate as Completion (EAC)
answer
The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
question
Estimate Costs
answer
The process of developing an approximation of the monetary resouces needed to complete project activities.
question
Estimate to Complete (ETC)
answer
The expected cost to finish all the remaining project work.
question
Execute
answer
Directing, managing, performing, and accomplishing the project work; providing the deliverables; and providing work performance information.
question
Executing Process Group
answer
Those processess performed to complete the work defined in the project management plan to satisfy the project specifications.
question
Expected Monetary Value (EMV) Analysis
answer
A statistical technique that calculates the average outcome when the future includes scenarios that may or may not happen. A common use of this technique is within deicsion tree analysis.
question
Expert Judgment
answer
Judgement provided based upon expertise in an application area, knowledge area, discipline, industry, etc., as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training.
question
External Dependency
answer
A relationship between project activities and non-project activities.
question
Facilitated Workshops
answer
An elicitation technique using focussed sessions that bring key cross-functional stakeholder together to define product requirements.
question
Failure Mode and Effect Analysis (FMEA)
answer
An analytical procedure in which each potential failure mode in every component of a product is analyzed to determine its effect on the reliability of that component and, by itself or in combinaison with other possible failure modes, on the reliability of the product or system and on the required function of the component; or the examination of a product(at the system and/or lower levels) for all ways that a failure may occur. For each potential failure, an estimate is made of its effect on the total system and of its impact. In addition, a review is undertaken of the action planned to minimize the probability of failure and to minimize its effects.
question
Fallback Plan
answer
Fallback plans inculde an alternative set of actions and tasks available in the event that the primary plan needs to be abandoned because of issues, risks, or other causes.
question
Fast Tracking
answer
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
question
Fee
answer
Represents profit as a component of compensation to as seller.
question
Finish Date
answer
A point in time associated with a schedule activity's completion. Usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, baseline, target, or current.
question
Finish-to-Finish (FF)
answer
A logical realtionship in which a successor activity cannot finish until a predecessor activity has finished.
question
Finish-to Start (FS)
answer
A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
question
Firm-Fixed-Price Contract (FFP)
answer
A type of fixed proce contract where buyer pays the seller a set amount (as defined by the contract), regardless of the seller's costs.
question
Fixed Formula Method
answer
An earned value method for assigning a specified percentage of budget value for a work package to the start mileston of the work package with the remaining budget value percentage assigned when the work package is complete.
question
Fixed Price Incentive Fee Contract (FPIF)
answer
A type of contract where the buyer pays the seller a set amount(as defined by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria.
question
Fixed Price with Economic Price Adjustment Contracts (FP-EPA)
answer
A fixed-price contract, but with a special provision allowing for predefined final adjustements to the contract price due to changed conditions, such as inflation changes, or cost increases (or decreases) for specific commodities.
question
Fioxed-Price Contracts
answer
An agreement that sets the fee that will be paid for a defined scope of work regardless of the cost or effort to deliver it.
question
Flowchart
answer
The depiction in a diagram format of the inputs, process actions, and outputs of one or more processes within a system.
question
Focus Groups
answer
An elicitation technique that brings together prequalified stakeholdes and subjet matter experts to learn about their expectations and attittides about a proposed product, service, or result.
question
Forecast
answer
An estimate or prediction of conditions and events in the project's future based on information and knowledge available at the time of the forecast. The information is based on the project's past performance and expected future performance, and includes information that could impact the project in the future, such as estimate at completion and estimate to complete.
question
Forward Pass
answer
A critical patch method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
question
Free Float
answer
The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
question
Functional Manager
answer
Someone with management authority over an organizational unit within a cuntional organization. The manager of any group that actually makes a product or performs a service. Sometimes called a line manager.
question
Functional Organization
answer
A hierarchical organization where employee has one clear superior, and staff are grouped by areas of specialization and managed by a person with expertise in that area.
question
Funding Limit Reconciliation
answer
The process of comparing the planned expenditure of project funds against any limits on the commitment of funds for the project to identify any variances between the funding limits and the planned expenditures.
question
Gantt Chart
answer
A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates.
question
Grade
answer
A category or rank used to distinguish items that have the same functional use (e.g., "hammer") but do not share the same requirements for quality (e.g., differetn hammers may need to withstand different amounts of force).
question
Ground Rules
answer
Expectations regarding acceptable bahavior by project team members.
question
Group Creativity Techniques
answer
Techniques that are used to generate ideas within a group of stakeholders.
question
Group Decision-Making Techniques
answer
Techniques to assess multiple alternatives that will be used to generate, classify, and prioritize product requirements.
question
Guideline
answer
An official recommendation or advice that indicates policies, standards, or procedures for how something should be accomplished.
question
Histogram
answer
A special form of bar chart used to describe the central tendency, dispersion, and shape of a statistical distribution.
question
Historical Information
answer
Documents and data on prior projects including project files, records, correspondence, closed contracts, and closed projects.
question
Human Resource Management Plan
answer
A component of the project management plan that describes how the roles and responsibilities, reporting relationships, and staff management will be addressed and structured.
question
Idea/Mind Mapping
answer
Technique used to consolidate ideas created through individual brainstroming sessions into a single map to reflec commonatily and differences in understanding and to generate new ideas.
question
Identify Risks
answer
The process of determining which risks may affedt the project and documenting their characteristics.
question
Identify Stakeholders
answer
The process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project; and analyzing and documenting relevant information regarding their interest, involvement, interfependencies, influence, and potential impact on project success.
question
Imposed Date
answer
A fixed date imposed on a schedule activity or schedule milestons, usually in the form of a "start no earlier than" and "finish no later than" date.
question
Incentive Fee
answer
A set of financial incentives related to cost, schedule, or technical performance of the seller.
question
Incremental Life Cycle
answer
A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team's understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product.
question
Independent Estimates
answer
A process of using a third party to obtain and analyze information to support prediction of cost, schedule, or other items.
question
Influence Diagram
answer
A graphical representation of situations showing causal influences, time ordering of events, and other relationshops among variables and outcomes.
question
Information Gathering Techniques
answer
Repeatable processes used to assemble and organize data across a sprectrum of sources.
question
Information Management Systems
answer
Facilities, processes, and procedures used to collect, store, and distribute information between producers and consumers of information in physical or electronic format.
question
Initiating Process Group
answer
Those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase.
question
Input
answer
Any time, wheter internal or external to the project that is required by a process before that process proceeds. May be an output from a predecessor process.
question
Inspection
answer
Examining or measuring to verify whether an activity, component, product, result, or service conforms to specified requirements.
question
Inspections and Audits
answer
A process to observe performance of contracted work or a promised product against agreed-upon requirements.
question
Interpersonal Skills
answer
Ability to establsh and maintain relationships with other people.
question
Interrelationship Diagraphs
answer
A quality management planning tool. the interrelationship diagraphs provide a process for creative problem-solving in moderately complex scenarios that possess intertwined logical realtionships.
question
Interviews
answer
A formal or informal approach to elicit information from stakeholders by taking to them directly.
question
Invitation for Bid (IFB)
answer
Generally, this term is equivalent to request for proposal. However, in some application areas, it may have a narrower or more specific meaning.
question
Issue
answer
A point or matter in question or in dispute, or a point or matter that is not settled and is under discussion or over which there are opposing views or disagreements.
question
Issue Log
answer
A project document used to document and monitor elements under discussion or in dispute between project stakeholder.
question
Iterative Life Cycle
answer
A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team's understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product.
question
Lag
answer
The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
question
Late Finish Date (LF)
answer
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.
question
Late Start Date (LS)
answer
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints.
question
Lead
answer
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
question
Lesson Learned
answer
The knowledge gained during a project which shows how project events were addressed or should be addressed in the future with purpose of improving future performance.
question
Lessons Learned Knowledge Base
answer
A store of historical information and lessons learned leraned about both the outcomes of previous project selection decisions and previous project performance.
question
Level of Effort (LOE)
answer
An activity that does not produce definitive end product and is measured by the passage of time. [Not: Level of effort is one of three earned valued management (EVM) types of activities used to measure work performance.]
question
Log
answer
A document used to record and describe or denote selected items identified during execution of a process or activity. Usually used with a modifier, such as issue, quality control, action, or defect.
question
Logical Relationship
answer
A dependency between two activities, or between an activity and a milestone.
question
Majority
answer
Support from more than 50 percent of the members of the group.
question
Make-or-Buy Analysis
answer
The process of gathering and organizing data about product requirements and analysing them against available alternatives including the purchase or internal manufacture of the product.
question
Manage Communications
answer
The process of creating, collecting, distributing, storing, retrieving, and the ultimate disposition of project information in accordance with the communications management plan.
question
Manage Project Team
answer
The process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance.
question
Manage Stakeholder Engagement
answer
The process of coomunicating and working with stakeholder to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle.
question
Management Reserve
answer
An amount of the project budget withhld for management control purposes. These are budgets reserved for unforeseen work that is within scope of the project. The management reserve is not included in the performance measurement baseline (PMB).
question
Management Skills
answer
The ability to plan, organize, direct, and control individuals or groups of people to achieve specific goals.
question
Manadatory Dependency
answer
A relationship that is contractually required or inherent in the nature of the work.
question
Market Research
answer
The process of gathering information at conferences, online reviews, and a variety of sources to identify market capabilities.
question
Master Schedule
answer
A summary-level project schedule that identifies the major deliverables and work breakdown structure components and key schedule milestones.
question
Material
answer
The aggregate of things used by an organization in any undertaking, such as equipment, apparatus, tools, machinery, gear, material, and supplies.
question
Matrix Diagrams
answer
A quality amangement and control tool used to perform data analysis within the organizational structure created in the matrix. The matrix diagram seeks to show the strength of relationships between factors, causes, and objectives that exist between the rows and columns that form the matrix.
question
Matrix Organization
answer
Any organizational structure in which the project manager shares responsability with the functional managers for assigning priorities and for directing the work of persons assigned to the project.
question
Methodology
answer
A system of practices, techniques, procedures, and rules used by those who work in a discipline.
question
Milestone
answer
A significant point or event in a project, program, or portfolio.
question
Milestone List
answer
A list identifying all project milestones and normally indicates whetehr the milestons is mandatory or optional.
question
Milestone Schedule
answer
A summary-level schedule that identifies the major schedule milestones.
question
Monitor
answer
Collect project performance data with respect to a plan, produce performance measures, and report and disseminate performance information.
question
Monitor and Control Project Work
answer
The process of tracking, reviewing, and reporting the progress to meet the performance objectives defined in the project management plan.
question
Monitoring and Controlling Process Group
answer
Those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes.
question
Monte Calro Simulation
answer
A process which generates hunderd or thousands of probable performance outcomes based on probability distributions for cost and schedule on individual tasks. The outcomes are then used to generate a probability distribution for the project as a whole.
question
Most Likely Duration
answer
An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
question
Multi-Criteria Decision Analysis
answer
This technique utilizes a decision matrix to provide a sstematic analytical approach for establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas.
question
Near-Critical Activity
answer
A schedule activity that has low total float. The concept of near-critical is equally applicable to a schedule activity or schedule network path. The limit below which total float is considered near critical is subject to expert judgmeent and vaires from project to project.
question
Negotiated Settlements
answer
The process of reaching final equitable settlement of all outstanding issues, claims, and disputes through negotiation.
question
Negotiation
answer
The process and activities to resolving disputes through consultations between involved parties.
question
Network Logic
answer
The collection of schedule activity dependencies that makes up a project schedule network diagram.
question
Network Path
answer
Any continuous series of schedule activities connected with logical relationships in a project schedule network diagram.
question
Networking
answer
Establishing connections and relationships with other people from the same or other oganizations.
question
Node
answer
One of the defining points of a schedule network; a junction point joined to some or all of the other dependency lines.
question
Nominal Group Techniques
answer
A technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming of for prioritization.
question
Nonconformance Work
answer
In the cost of quality framework, -------- -------- is done to deal with the consequences of errors and failures in doing activities correctly on the first attempt. In efficient quality management systems, the amount of -------- -------- will approach zero.
question
Objective
answer
Something toward which work is to be directed, a strategic position to be attained, a purpose to be achieved, a result to be obtained, a product to be produced, or a service to be performed.
question
Observations
answer
A technique that provides a direct way of viewing individuals in their environement performing their jobs or tasks and carrying out processes.
question
Opportunity
answer
A risk that would have a positive effect on one or more project objectives.
question
Optimistic Duration
answer
An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
question
Organizational Breakdown Structure (OBS)
answer
A hierarchical representation of the project organization that illustre the relationship between project activities and the organizational units that will perfrom those activities.
question
Organizational Process Assets
answer
Plann, processes, policies, procedures, and knowledge bases that are specific to and used by the performing organization.
question
Organizational Project Management Maturity
answer
The level of an organization's ability to deliver the desired strategic outcomes in a predictable, controllable, and releable manner.
question
Output
answer
A product, result, or service generated by a process. May be an input to a successor process.
question
Parametric Estimating
answer
An stimating technique in which an alogirthm is used to calculate cost or duration based on historical data and project parameters.
question
Pareto Diagram
answer
A histogram, ordered by frequency of occurance, that shows how many results were generated by each identified cause.
question
Path Convergence
answer
A relationship in which a schedule activity has more than one predecessor.
question
Path Divergence
answer
A relationship in which a schedule activity has more than one successor.
question
Payment Systems
answer
The system used to provide and track supplier's invoices and payments for services and products.
question
Percent Complete
answer
An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
question
Perform Integrated Change Control
answer
The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational prcess assets, project documents, and the project management plan; and communicating their disposition.
question
Perform Qualitativ Risk Analysis
answer
The process of prioritizing risks for further analysis or action by assassing and combinung their probabability of occurence and impact.
question
Perform Quality Assurance
answer
The process of auditing the quaility requirements and the results from quality control measurements to ensure that appropriate quality standards and operational definitions are used.
question
Perform Quantitative Risk Analysis
answer
The process of numerically analyzing the effect of identified risks on overall project objectives.
question
Performance Measurement Baseline
answer
An approved, integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance. The -------- -------- -------- includes contingency reserve, but excludes management reserve.
question
Performance Reviews
answer
A techniqu that is used to measure, compare, and analyze actual performance of work in progress on the project against the baseline.
question
Performing Organization
answer
An enterprise whose personnel are most directly involved in doing the work of the project or program.
question
Pessimistic Duration
answer
Estimate of the longest activity duration that takes into account all of the known variables that could affect performance.
question
Phase Gate
answer
A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program.
question
Plan Communications Management
answer
The process of developing an appropriate approach and plan for project communications based on stakeholder's information needs and requirements and available organizational assets.
question
Plan Cost Management
answer
The process that establish the policies, procedures, and documentation for planning, managing, expending, and controlling project costs.
question
Plan Human Resource Management
answer
The process of identifying and documenting project roles, responsibilities, required skilss, reporting relationships, and creating a staffing management plan.
question
Plan Procurement Management
answer
The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.
question
Plan Quality Management
answer
The process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements.
question
Plan Risk Management
answer
The process of defining how to conduct risk management activities for a project.
question
Plan Risk Responses
answer
The process of developing options and actions to enhance opportunities and to reduce threats to project objectives.
question
Plan Schedule Management
answer
The process of establshing the plocieis, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
question
Plan Scope Management
answer
The process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled.
question
Plan Stakeholder Management
answer
The process of developing appropriate management strategies to effectively engage stakeholdes throughout the project life cycle, based on the analyis of thier needs, interests, and potential impact on project success.
question
Planned Value (PV)
answer
The authorized budget assigned to scheduled work.
question
Planning Package
answer
A work breakdown structure component below the control account with known work content but without detailed schedule activities.
question
Planning Process Group
answer
Those processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.
question
Plurality
answer
Decisions made by the largest block in a group, even if a majority is not achieved.
question
Policy
answer
A structured pattern of actions adopted by an organization such that the organization's policy can be explained as a set of basic principles that govern the organization's conduct.
question
Portfolio
answer
Projects, programs, subportfolios, and operations managed as a group to achieve strategic objectives.
question
Portfolio Management
answer
The centralized management of one or more portfolios to achieve strategic objectives.
question
Practice
answer
A specific type of professional or management activity that contributes to the execution of a process and that may employ one or more techniques and tools.
question
Precedence Diagramming Method (PDM)
answer
A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
question
Precedence Relationship
answer
The term used in the precedence diagramming method for a logical realtionship. In cureent usage, however, precedence relationship, logical relationship, and dependency are widely used interchangeably regardless of the diagramming method used.
question
Precision
answer
Within the quality management system, -------- is a measure of exactness.
question
Precessor Activity
answer
An activity that logically comes before a dependent activity in a schedule.
question
Predictive Life Cycle
answer
A form of project life cycle in which the project scope, and the time and cost required to deliver that scope, are determined as early in the life cycle as possible.
question
Preventive Action
answer
An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
question
Prioritization Matrices
answer
A quality management planning tool used to identify key issues and evaluate suitable alternatives to define a set of implementations priorities.
question
Probabilitiy and Impact Matrix
answer
A grid for mapping the probability of each risk occurence and its impact on project objectives if that risk occurs.
question
Procedure
answer
An established method of accomplishing a consistent performance or result, a procedure typically can be describes as the sequence of steps that will be used to execute a process.
question
Process
answer
A systematic series of activities directed towards causing an end result such that one or more inputs will be acted upon create one or more outputs.
question
Process Analysis
answer
A -------- -------- follows the steps outlined in the process improvement plan to identify needed improvements.
question
Process Decision Program Charts (PDPC)
answer
The -------- -------- -------- -------- is used to understand a goal in relation to the steps for getting to the goal.
question
Process Improvement Plan
answer
A subsidiary plan of the project management plan. It details the steps for analyzing processes to identify activities that enhance their value.
question
Procurement Audits
answer
The review of contracts and contracting processes for completeness, accuray, and effectiveness.
question
Procurement Documents
answer
The documents utilized in bid and proposal activities, which include the buyer's Invitation for Bid, Invitation for Negotiations, Request for Information, Request for Quaotation, Request for Proposal, and seller's responses.
question
Procurement Management Plan
answer
A component of the project or program management plan that describes how a project team will acquire goods and services from outside the performing organization.
question
Procurement Performance Reviews
answer
A structured review of the seller's progress to deliver project scope and quality, whithin cost and on schedule, as compared to the contract.
question
Procurement Statement of Work
answer
Describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results.
question
Product
answer
An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item. Additional words for products are material and goods.
question
Product Analysis
answer
For projects that have a product as a deliverable, it is a tool to define scope that generally means asking quastions about a product and forming answers to describes the use, characteristics, and other relevant aspects of what is going to be manufactured.
question
Product Life Cycle
answer
The series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement.
question
Product Scope.
answer
The features and functions that characterize a product, service, or result.
question
Product Scope Description
answer
The documentated narrative description of the product scope.
question
Program
answer
A group of related projects, subprograms, and program activities managed in a coordinated way to obtain benefits not available from managing them individually.
question
Program Evaluation and Review Technique (PERT)
answer
A technique for estimating that applies a weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.
question
Program Management
answer
The application of knowledge, skills, tools, and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
question
Progressive Elaboration
answer
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
question
Project
answer
A temporary endeavor undertaken to create a unique product, service, or result.
question
Project-Based Organizations (PBOs)
answer
A variety of organizational forms that involve the creation of temporary systems for the performance of projects. PBOs conduct the majority of their activities as projects and/or provide project over functional approaches.
question
Project Calendar
answer
A calendar that identifies working days and shifts that are available for schedule activities.
question
Project Charter
answer
A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
question
Project Communications Management
answer
-------- -------- -------- inculdes the process that are required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval management, control, monitoring, and the ultimate disposition of project information.
question
Project Cost Management
answer
-------- -------- -------- includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget.
question
Project Funding Requirements
answer
Forecast project costs to be paid that are derivated from the cost baseline for total or periodic requirements, including projected expenditures plus anticipated liabilities.
question
Project Governance
answer
The alignment of project objectives with the strategy of the larger organization by the project sponsor and project team. A -------- -------- is defined by and is required to fit within the larger context of the program or organization sponsoring it, but is separate from organizational governance.
question
Project Human Resource Management
answer
-------- -------- -------- -------- inculdes the processes that organize, manage, and lead the project team.
question
Project Initiation
answer
Launching a process that can result in the authorization of a new project.
question
Project Integration Management
answer
-------- -------- -------- includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.
question
Project Life Cycle
answer
The series of phases that a project passes through from its initiation to its closure.
question
Project Management
answer
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
question
Project Management Body of Knowledge
answer
An inclusive term that describes the sum of knowledge within the profession of project management. As with other professions, such as law, medicine, and accounting, the -------- -------- -------- rests with practitioners and academics that apply and advance it. The complete -------- -------- -------- -------- -------- includes proven traditional practices that are widely applied and innovative practices that are emerging in the professions. -------- -------- -------- includes both published and unpublished materials. This -------- -------- -------- is constantly evolving.PMI's -------- -------- -------- -------- -------- identifies a subset of the -------- -------- -------- -------- -------- that is generally recognized as good practice.
question
Project Management Information System
answer
An information system consisting of the tools and techniques used to gather, integrate, and disseminate the outpus of project management processes. It is used to support all aspects of the project from initiating through closing, and can include both manual and automated systems.
question
Project Management Knowledge Area
answer
An identified area of project management defined by its knowledge requirements and described in terms of its component processes, practices, inputs, outputs, tools, and techniques.
question
Project Management Office (PMO)
answer
An organizational structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.
question
Project Management Plan
answer
The document that describes how the project will be execute, monitored and controlled.
question
Project Management Process Group
answer
A logical grouping of project management inputs, tools and techniques, and outputs. The -------- -------- -------- -------- include initiating processes, planning processes, executing processes, monitoring and controlling processes, and closing processes. -------- -------- -------- -------- are not project phases.
question
Project Management Staff
answer
The members of the project team who perform project management activities such as schedule, communications, risk management, etc.
question
Project Management System
answer
The aggregation of the processes, tools, techniques, methodologies, resources, and procedures to manage a project.
question
Project Management Team
answer
The members of the project team who are directly involved in project management activities. On some smaller projects, the project management team may include virtually all of the project team members.
question
Project Manager (PM)
answer
The person assigned by the performing organization to lead the team members and their interrelationships for a specific project.
question
Project Organization Chart
answer
A document that graphically depicts the project team members and their interrelationships for a specific project.
question
Project Phase
answer
A collection of logically related project activities that culminates in the completion of one or more deliverables.
question
Project Procurement Management
answer
Project Procurement Management includes the processes necessary to purchase or acquire products, service, or results needed from outside the project team.
question
Project Quality Management
answer
-------- -------- -------- includes the processes and activities of the performing organization that determine quality policies, objectives, and responsibilities so that the project will satisfy the needs for which it was undertaken.
question
Project Risk Management
answer
-------- -------- -------- includes the processes of conducting risk management planning, identification, analysis, responses planning, and controlling risk on a project.
question
Project Schedule
answer
An output of a schedule model that presetns linked activities with planned dates, durations, milestones, and resources.
question
Project Schedule Network Diagram
answer
A graphical representation of the logical relationships among the project schedule activities.
question
Project Scope
answer
The work performed to deliver a product, service, or result with the specified features and functions.
question
Project Scope Management
answer
-------- -------- -------- includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
question
Project Scope Statement
answer
The description of the project scope, major deliverables, assumptions, and constraints.
question
Project Stakeholder Management
answer
-------- -------- -------- includes the processes required to identitfy the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholde expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution.
question
Project Team
answer
A set of individuals who support the project manager in performing the work of the project to achieve its objectives.
question
Project Team Directory
answer
A documented list of project team members, their project roles, and communication information.
question
Project Time Management
answer
-------- -------- -------- includes the processes required to manage the imely completion of the project.
question
Projectized Organization
answer
Any organizational structure in which the project manager has full authority to assign priorities, apply resources, and direct the work of persons assigned to the project.
question
Proposal Evaluation Techniques
answer
The process of reviewing proposals provided by suppliers to support contract award decisions.
question
Prototypes
answer
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it.
question
Quality
answer
The degree to witch a set of inherint characteristics fulfulls requirements.
question
Quality Audits
answer
A quality audit is a structures, independent process to determine if project activities comply with organizational and project policies, processes, and procedures.
question
Quality Checklists
answer
A structured tool used to verify that a set of required steps has been performed.
question
Quality Control Measurements
answer
The documented results of control quality activities.
question
Quality Function Deployment (QFD)
answer
A facilitated workshop technique that helps to determine critical characteristic for new product development.
question
Quality Management and Control Tools
answer
They are a type of quality planning tools used to link and sequence the activities identified.
question
Quality Management Plan
answer
A component of the project or program management plkan that describes how an organization's quality policies will be implemented.
question
Quality Management System
answer
The organizational framework whose structure provides the policies, processes, procedures, and resources required to implement the qualty management plan. The typical project quality management plan shoul be compatible to the organization's -------- -------- --------.
question
Quality Metrics
answer
A description of a project or product attribute and how to measure it.
question
Quality Policy
answer
A policy specific to the Project Quality Management Knowledge Area, it establishes the basic principles that shoul govern the organization's actions as it implements its system for quality management.
question
Quality Requirement
answer
A condition or capability that will be used to assess conformance by validating the acceptability of an attribute for the quality of a result.
question
Quantitative Risk Analysis and Modeling Techniques
answer
Commonly used techniques for both event-oriented and project-oriented analysis approaches.
question
Questionnaires and Surveys
answer
Written sets of questions designed to quickly accumulate information from a large number of respondents.
question
RACI
answer
A comon type of responsability assignment matrix that uses responsible, accountable, consult, and inform statuses to define the involvement of stakeholdes in project activities.
question
Records Management System
answer
A specific set of processes, related control functions, and tools that are consolidated and combined to record and retain information about the project.
question
Regression Analysis
answer
An analytic technique where a series of input variables are examined in relation to their corresponding output results in order to develop a mathematical or statistical relationship.
question
Regulation
answer
Requirements imposed by a governmental body. There requirements can establish product, process, or service characteristics, including applicable administrative provisions that have government-mandated compliance.
question
Reporting Systems
answer
Facilities, processes, and procedures used to generate of consolidate repots from one or more information management systems and facilitate report distribution to the project stakeholders.
question
Request for Information (RFI)
answer
A type of procurement document whereby the buyer requests a potential seller to provide various pieces of information related to a product or service or seller capability.
question
Request for Proposal (RFP)
answer
A type of procurement document used to request proposals from prospective sellers of products or services. In some application areas, it may have a narrower or more specific meaning.
question
Request for Quotation (RFQ)
answer
A type of procurement document used to request price quotations from prospectices sellers of common or standard products or services. Sometimes used in place of request for proposal and, in some application areas, it may have a narrower or more specific meaning.
question
Requested Change
answer
A formally documented change request that is submitted for approval to the integrated change control process.
question
Requirement
answer
A condition or capability that is required to be present in a product, service, or result to satisfy a contract or other formally imposed specification.
question
Requirements Documentation
answer
A description of how individual requirements meet the business need for the project.
question
Requirements Management Plan
answer
A component of the project or program management plan describes how requirements will be analyzed, documentet, and managed.
question
Requirements Traceability Matrix
answer
A grid that links product requirements from their origin to the deliverables that satify them.
question
Reserve
answer
A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management --------, contingency -------- ) to provide further detail on what types of risk are meant to be mitigated.
question
Reserve Analysis
answer
An analytical technique to detemrine the essentail features and relationshops of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project.
question
Residual Risk
answer
A risk that remains after risk responses have been implemented.
question
Resource
answer
Skilled human resources (specific disciplines either individually or in crews or teams), equipment, services, supplies, commodities, material, budget, or funds.
question
Resource Breakdown Structure
answer
A hierarchical representation of resources by category and type.
question
Resource Calendar
answer
A calendar that identifies the working days and shifts on which each specific resource is available.
question
Resource Histogram
answer
A bar chart showing the amount of time that a resource is scheduled to work over a series of time periods. Resorce availability may be depicted as a line for comparison purposes. Contrasting bars may sho actual amounts of resources used as the project progresses.
question
Resource Leveling
answer
A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
question
Resource Optimization Techniques
answer
A technique that is used to adjust the start and finish dats of activities that adjust planned resource use to be equal to or less than resource availability.
question
Resource Smoothing
answer
A technique which adjusts the activities of a schedule model such that the requirement for resources on the project do not exceed certain predefined resource limits.
question
Responsibility
answer
An assignment that can be delegated within a project management plan such that the assigned resource incurs a duty to perform the requirements of the assignment.
question
Responsibility Assignment Matrix (RAM)
answer
A grid that shows the project resources assigned to each work package.
question
Result
answer
An output from performing project management processes and activities. -------- include outcomes (e.g., integrated systems, revised process, restructured organization, tests, trained personnel, etc.) and document (e.g., policies, plans, studies, procedures , specifications, reports, etc.).
question
Rework
answer
Action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
question
Risk
answer
An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.
question
Risk Acceptance
answer
A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
question
Risk Appetite
answer
The degree of uncertainty an entity is willing to take on, in anticipation of a reward.
question
Risk Audits
answer
Examination and documentation of the effectiveness of risk responses in dealing with identified risks and their root causes, as well as the effectiveness of the risk management process.
question
Risk Avoidance
answer
A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
question
Risk Breakdown Structure (RBS)
answer
A hierarchical representation of risks according to their risk categories.
question
Risk Categorization
answer
Organization by sources of risk (e.g., using the RBS), the area of the project affected (e.g., using WBS), or othe useful category (e.g., project phase) to determine the areas of the project most exposed to the effects of uncertainty.
question
Risk Category
answer
A group of potential causes of risk.
question
Risk Data Quality Assessment
answer
Technique to evaluate the degree to which the data about risks is useful for risk management.
question
Risk Management Plan
answer
A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.
question
Risk Mitigation
answer
A risk response strategy whereby the project team acts to reduce the probability of occurence or impact of a risk.
question
Risk Reassessment
answer
-------- -------- is the identification of new risks, reassessment of current risks, and the closing of risks that are outdated.
question
Risk Register
answer
A document in which the results of risk analysis and risk response planning are recorded.
question
Risk Threshold
answer
Measure of the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Below that -------- --------, the organization will accept the risk. Above that -------- --------, the organization will not tolerate the risk.
question
Risk Tolerance
answer
The degree, amount, or volume of risk that an organization or individual will withstand.
question
Risk Transference
answer
A risk response strategy whereby the project team shifts the impact of a threat ro a third party, together with ownership of the response.
question
Risk Urgency Assessment
answer
Review and determiation of the timing of actions that may need to occur sooner than other risk items.
question
Role
answer
A defined function to be performed by a project team member, such as testing, filing, inspecting, or coding.
question
Rolling Wave Planning
answer
An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.
question
Root Cause Analysis
answer
An analytical technique used to determine the basic underlying reason that causes a variance or a defect or a risk. A -------- -------- -------- underlie more thant one variance or defect or risk.
question
Scatter Diagram
answer
A correlation chart that uses a regression line to explain or to predict how the change in an independent variable will change a dependent variable.
question
Schedule Baseline
answer
The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
question
Schedule Compression
answer
Techniques used to shorten the schedule duration without reducing the project scope.
question
Schedule Data
answer
The collection of information for describing and controlling the schedule.
question
Schedule Foercasts
answer
Estimates or predictions of conditions and events in the project's future based on information and knowledge available at the time the schedule is calculated.
question
Schedule Management Plan
answer
A component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.
question
Schedule Model
answer
A representation of the plan for executing the project's activities including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts.
question
Schedule Network Analysis
answer
The technique of identifying early and late start dates, as well as early and late finish dates, for the uncompleted portions of project schedule activities.
question
Schedule Network Templates
answer
A set of activities and relationships that have been established that can be used repeatedly for a particular application area or an aspect of the project where a prescribed sequence is deisred.
question
Schedule Performance Index (SPI)
answer
A measure of schedule efficiency expressed as the ratio of earned value to planned value.
question
Schedule Variance (SV)
answer
A measur of schedule performance expressed as the difference between the earned value and the planned value.
question
Scheduling Tool
answer
A tool that provides schedule component names, definitions, structural realtionships, and formats that support the application of a scheduling method.
question
Scope
answer
The sum of the products, services, and results to be provided as a project.
question
Scope Baseline
answer
The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison.
question
Scope Change
answer
Any change to the project scope. A -------- -------- almost always requires an adjustement to the project cost or schedule.
question
Scope Creep
answer
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.
question
Scope Management Plan
answer
A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and verified.
question
Secondary Risk
answer
A risk that arises as a direct result of implementing a risk response.
question
Selected Sellers
answer
The selles which habe been selected to provide a contracted set of services or products.
question
Seller
answer
A provider or supplier of products, services, or results to an organization.
question
Seller Proposals
answer
Formal responses from sellers to a request for proposal or other procurement documentspecifying the priice, commercial terms of sale, and technical specifications or capabilities the seller will do for the requesting organization that, if accepted, would bind the seller to perform the resulting agreement.
question
Sensistivity Analysis
answer
A quantitative risk anylsis and modeling technique used to help determine which risks have the most potential impact on the project. It examines the extent to which the uncertainty of each project element affects the objective being examined when all other uncertain elements are held at their baseline valus. The typical display of results is in the form of a tornado diagram.
question
Sequence Activities
answer
The process of identifying and documenting relationships among the project activities.
question
Seven Basic Quality Tools
answer
A standard toolkit used by quality management professionals who are responsible for planning, monitoring, and controlling the issues related to quality in an organization.
question
Simulation
answer
A -------- usesa project model that translates the uncertainties at a detailed level into their potential impact on objectvies that are expressed at the level of the total project. Project -------- use computer models and estimates of risk, usually expressed as a probability of possible costs or durations at a detailled work level, and re typically performed using Monte Carlo analysis.
question
Source Selection Criteria
answer
A set of attributes desired by the buyer which a seller is required to meet or exceed to be selected for a contract.
question
Specification
answer
A document that specifies, in a complete, precise, verifiable manner, the requirements, desing, behavior, or other characteristics of a system, component, product, result, or service and the procedures for determining whether these provisions have been satisfied. Examples are: requirement --------, design --------, product --------, and test --------.
question
Specification Limits
answer
The area, on either side of the centerline, or mean, of data plotted on a control chart that meets the customer's requirements for a product or service. This area may be greater than or less than the area defined by the control limits.
question
Sponsor
answer
A person or group who provides resources and support for the project, program, or portfolio and is accountable for enabling success.
question
Sponsoring Organization
answer
The entity responsible for providing the project's sponsor and a conduit for project funding or other project resources.
question
Staffing Management Plan
answer
A component of the human resource plan that describes when and how project team members will be acquired and how long they will be needed.
question
Stakeholder
answer
An individual, group, or organization who may affect, be affected by, or perceive itself to be affectedby a decision, activity, or outcome of a project.
question
Stakeholder Analysis
answer
A technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.
question
Stakeholder Management Plan
answer
The -------- -------- -------- is a subsidiary plan of the project management plan that defines the processes, procedures, tools, and techniques to effectively engage stakeholders in project decisions and execution based on the analysis of their needs, interests, and potential impact.
question
Stakeholder Register
answer
A project document including the identification, assessment, and classification of project stakeholders.
question
Standard
answer
A document that provides , for common and repeated use, ruls, guidelines, or characteristics for activities or their results, aimed at the achievement of the optimum degree of order in a given context.
question
Start Date
answer
A point in time associated with a schedule activity's start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current.
question
Start-to-Finish (SF)
answer
A logical realtionship in which a successor activity cannot finish until a predecessor activity has started.
question
Start-to-Start (SS)
answer
A logical relationship in which a successor activity cannot start until a predecessor activity has started.
question
Statement of Work (SOW)
answer
A narrative description of products, services, or results to be delivered by the project.
question
Statistical Sampling
answer
Choosing part of a population of interest for inspection.
question
Subnetwork
answer
A subdivision (fragment) of a project schedule network diagram, usually representing a subproject or a work package. Often used to illustrate or study some potential or proposed schedule condition, such as changes in preferential schedule logic or project scope.
question
Subproject
answer
A smaller portion of the overall project created when a project is subdivided into more manageable components or pieces.
question
Successor Activity
answer
A dependent activity that logically comes after another activity in a schedule.
question
Summary Activity
answer
A group of related schedule activities aggregated and displayed as a single activitiy.
question
SWOT Analysis
answer
Analysis of strenghs, weaknesses, opportunities, and threats of an organization, project, or option.
question
Tailor
answer
The act of carefully selecting process and related inputs and outputs contained within the PMBOK Guide to determine a subset of specific processes that will be included within a project's overall management approach.
question
Technique
answer
A defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service, and that may employ one or more tools.
question
Templates
answer
A partially complete document in a predefined format that provides a defined structure for collecting, organizing, and presenting information and data.
question
Threat
answer
A risk that would have a negative effect on one or more project objectives.
question
Three-Point Estimate
answer
A technique used to estimate cost or duration by applying an average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.
question
Threshold
answer
A cost, time, quality, technical, or resource value used as a parameter, and which may be included in product specifications. Crossing the -------- should trigger some action, such as generating an exception report.
question
Time and Material Contract (T&M)
answer
A type of contract that is a hybrid contractual arrangement containing aspects of both cost-reimbursable and fixed-rpice contracts. -------- -------- -------- -------- resemble cost-reimbursable type arrangements in that they have no definitce end, because the full value of the arrangement is not defined at the time of the ward. Thus, -------- -------- -------- -------- can grow in contract value as if they were cost-reimbursable-type arrangements. Conversely, -------- -------- -------- -------- can also resemble fixed-price arrangements. Foer example, the unit rates are preset by the buyer and seller, when both parties agree on the rates for the category of senior engineers.
question
Time-Scaled Schedule Network Diagram
answer
Any project schedule network diagram drawn in such a way that the positioning and length of the schedule activity represents its duration. Essentially, it is a bar chart that includes schedule network logic.
question
To-Complete Performance Index (TCPI)
answer
A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
question
Tolerance
answer
The quantified description of acceptable variation for the quality requirement.
question
Tornado Diagram
answer
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables.
question
Tool
answer
Something tangible, such as a template or software program, used in performing an activity to produce a product or result.
question
Total Float
answer
The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
question
Tree Diagram
answer
A systematic diagram of a decomposition hierarchy used to visualize as parent-to-child relationships a systematic set of rules.
question
Trend Analysis
answer
An analytical technique that uses mathematical models to forecast future outcomes based on historical results. It is a method of determining the variance from a baseline of a budget, cost, schedule, or scope parameter by using prior progress reporting periods' data and projecting how much that parameter's variance from baseline might be at some future point in the project if no changes are made in executing the project.
question
Trigger Condition
answer
An event or situation that indicates that a risk is about to occur.
question
Unanimity
answer
Agreement by everyone in the group on a single course of action.
question
Validate Scope
answer
The process of formalizing acceptance of the completed project deliverables.
question
Validation
answer
The assurance that a prodcut, service, or system meets the needs of the customer and other identified stakholders. It often involves acceptance and suitability with external customers.
question
Value Engineering
answer
An approach used to optimze project life cycle costs, save time, increase profits, improve quality, expand market share, solve problem, and/or use resources more effectively.
question
Variance
answer
A quantifable deviation, departure, or divergence away from a known baseline or expected value.
question
Variance Analysis
answer
A technique for determining the cause and degree of difference between the baseline and actual performance.
question
Variance at Completion (VAC)
answer
A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.
question
Variation
answer
An actual condition that is different from the expected condition that is contained in the baseline plan.
question
Velocity
answer
A measure of a team's productivity rate at which the deliverables are produces, validated, and accepted within a predefined interval. -------- is a capacity planning approach frequently used to forecast future project work.
question
Verification
answer
The evaluation of whether or not a product, service, or system complies with a regulation, requirement, specification, or imposed condition. It is often an interanl process.
question
Verified Deliverables
answer
Completed project deliverables that have been checked and confirmed for correctness through the Control Quality process.
question
Voice of the Customer
answer
A planning technique used to provide products, services, and results that truly reflect customer requirements by translating those customer requirements into the appropriate technical requirements for each phase of project development.
question
WBS Dictionary
answer
A document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure.
question
Weighted Milestone Method
answer
An earned value method that divides a work package into measurable segments, each ending with an observable mileston, and then assigns a weighted value to the achievement of each mileston.
question
What-If Scenario Analysis
answer
The process of evaluating scenarios in order to predict their effect on project objectives.
question
Work Authorization
answer
A permission and direction, typically written, to begin work on specific schedule activity or work package or control account. It is a method for sanctioning project work to ensure that the work is done by the identified organization, at the right time, and in the proper sequence.
question
Work Authorization System
answer
A subsystem of the overall project management system. It is a collection of formal documented procedures that defines how project work will be authorized (committed) to ensure that the work is done by the identified organization, at the right time, and in the proper sequence. It includes the steps, documents, tracking system, and defined approval levels needed to issue work authorizations.
question
Work Breakdown Structure (WBS)
answer
A hierarchical decompostion of the total scopeof work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
question
Work Breakdown Structure Component
answer
An entry in the work breakdown structure that can be at any level.
question
Work Package
answer
The word defined at the lowest level of the work breakdown structure for which cost and duration can be estimated and managed.
question
Work Performance Data
answer
The raw observations and measurements identified during activities being performed to carry out the project work.
question
Work Performance Information
answer
The performance data collected from various controlling processes, analyzed in context and integrated based on relationshops across areas.
question
Work Performance Reports
answer
The physical or electronic representation of work performance information compiled in project documents, intended to generate decisions, actions, or awareness.
question
Workaround
answer
A response to a threat that has occured, for which a prior response had not been planned or was not effective.
question
Activity Network Diagrams
answer
A graphical representation of the logical relationships among the project schedule activities.
question
Buffer
answer
A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management --------, contingency -------- ) to provide further detail on what types of risk are meant to be mitigated.
question
Charter
answer
A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
question
Contingency Allowance
answer
A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management --------, contingency -------- ) to provide further detail on what types of risk are meant to be mitigated.
question
Dependency
answer
A dependency between two activities, or between an activity and a milestone.
question
Fishbone diagram
answer
A decomposition technique that helps trace an undesirable effect back to ist root cause.
question
Float
answer
Also called slack. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
question
Hammock Activity
answer
A group of related schedule activities aggregated and displayed as a single activitiy.
question
Hard Logic
answer
A relationship that is contractually required or inherent in the nature of the work.
question
Leveling
answer
A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
question
Life Cycle
answer
The series of phases that a project passes through from its initiation to its closure.
question
Network
answer
A graphical representation of the logical relationships among the project schedule activities.
question
Network Analysis
answer
The technique of identifying early and late start dates, as well as early and late finish dates, for the uncompleted portions of project schedule activities.
question
Performance Reporting
answer
The physical or electronic representation of work performance information compiled in project documents, intended to generate decisions, actions, or awareness.
question
Performance Reports
answer
The physical or electronic representation of work performance information compiled in project documents, intended to generate decisions, actions, or awareness.
question
Phase
answer
A collection of logically related project activities that culminates in the completion of one or more deliverables.
question
Preferential Logic
answer
A relationship that is established base on knowledge of best practices within a particual application area or an aspect of the project where a specific sequence is desired.
question
Preferred Logic
answer
A relationship that is established base on knowledge of best practices within a particual application area or an aspect of the project where a specific sequence is desired.
question
Project Statement of Work
answer
A narrative description of products, services, or results to be delivered by the project.
question
Schedule
answer
An output of a schedule model that presetns linked activities with planned dates, durations, milestones, and resources.
question
Soft Logic
answer
A relationship that is established base on knowledge of best practices within a particual application area or an aspect of the project where a specific sequence is desired.
question
Team Members
answer
A set of individuals who support the project manager in performing the work of the project to achieve its objectives.