Unlock answersquestion
analogy approach
answer
creating a WBS by using a *similar project's WBS* as a starting point
question
benchmarking
answer
generating ideas by *comparing specific project practices or product characteristics* to those other projects or products inside or outside the performing organization
question
bottom-up approach
answer
creating a WBS by having team members identify as many specific tasks related to the project as possible and then grouping them into higher-level categories
question
decomposition
answer
*subdividing* project deliverables into small *pieces*
question
deliverable
answer
a product, such as a report or segment of software code, produced as part of a project
question
Joint Application Design (JAD)
answer
Using highly *organized and intensive workshops* to bring together project stakeholders-the sponsor, users, business analysts, programmers, and so on-to jointly define and design information systems
question
project scope management
answer
the processes involved in defining and controlling what work is or is not *included* in the project
question
project scope statement
answer
a document that includes at least a *description* of the project, including its overall objectives and justification, detailed descriptions of all project deliverables and the characteristics and requirements of products and services produced as part of the project
question
prototyping
answer
developing a *working replica* of the system or some aspect of it to help define user requirements
question
requirement
answer
a *condition or capability that must be met* by the project or that must be present in the product, service, or result, to satisfy an agreement or other formally imposed specification
question
requirements management plan
answer
a plan that describes how project requirements will be analyzed, documented and managed
question
requirements traceability matrix (RTM)
answer
A table that list requirements, their various attributes, and the status of the requirements to ensure that all are addressed
question
scope
answer
*all the work involved* in creating the products of the project and the processes used to create them
question
scope baseline
answer
the approved project scope statement and its associated WBS and WBS dictionary
question
scope creep
answer
the tendency for project scope to keep getting bigger
question
scope validation
answer
formal *acceptance* of the completed project *deliverables*
question
top-down approach
answer
Creating a WBS by starting with the largest items of the project and breaking them into subordinate items
question
use case modeling
answer
a process for identifying and modeling business events, who initiated them, and how the system should respond to them
question
variance
answer
the difference between planned and actual performance
question
WBS dictionary
answer
a document that includes detailed information about each WBS item
question
work breakdown structure (WBS)
answer
a *deliverable-oriented grouping of the work* involved in a project that defines its total scope
question
work package
answer
a task at the lowest level of the WBS
question
activity attributes
answer
info about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity
question
activity list
answer
a tabulation of activities to be included on a project schedule
question
arrow-on-arrow (AOA)
answer
a networking diagram technique in which activities are represented by arrows and connected at points called nodes to illustrate the sequence of activities; also called ADM
question
backward pass
answer
a project network diagramming technique that determines the late start and late finish dates for each activity
question
baseline dates
answer
the planned schedule dates for activities in a Tracking Gantt chart
question
buffer
answer
additional time to complete a task ; a buffer is added to an estimate to account for various factors
question
burst
answer
a single node followed by two or more activities on a network diagram
question
crashing
answer
a technique for making cost and schedule trade-offs to obtain the *greatest amount of schedule compression* for the *least incremental cost* ex: employee works 1 full time week instead of 2 weeks part time
question
critical chain scheduling
answer
a method of scheduling that takes *limited resources* into account when creating a project schedule and includes buffers to protect the project completion date
question
critical path
answer
the series of activities in a network diagram that determines the *earliest completion* of the project; it is the *longest path* through the ND and has the least amount of slack or float
question
critical path method (CPM) or critical path analysis
answer
a project network diagramming technique used to predict *total project duration*
question
dependency
answer
the sequencing of project activities or tasks; also called a relationship
question
discretionary dependencies
answer
the sequencing of project activities or tasks *defined by the project team* and used with care because they may limit later scheduling options
question
dummy activities
answer
activities with *no duration and no resources* used to *show a logical relationship* between two activities in the arrow diagramming method of project network diagrams
question
duration
answer
the actual amount of time worked on an activity plus elapsed time.
question
early finish date
answer
the *earliest possible time an activity can finish* based on the project network logic
question
early start date
answer
the *earliest possible time an activity can start* based on the project network logic
question
effort
answer
the number of workdays or work hours required to complete a task
question
external dependencies
answer
the sequencing of project activities or tasks that involve relationships between *project and non-project activities*
question
fast tracking
answer
a schedule compression technique in which you *do activities in parallel* that you would normally do in sequence
question
feeding buffers
answer
time added before tasks on the critical chain if they are preceded by other tasks that are not on the critical path
question
finish to finish dependency
answer
a relationship on a project network diagram in which the "from" activity must be finished before the "to" activity can be finished
question
finish to start dependency
answer
a relationship on a project network diagram in which the "from" activity must be finished before the "to" activity can be started
question
forward pass
answer
a network diagramming technique that determines the early start date and early finish dates for each activity
question
free slack (free float)
answer
the amount of time an activity can be delayed without delaying the *early start date* of any immediately following activities
question
Gantt chart
answer
a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a *calendar format*; bar charts
question
late finish date
answer
the latest possible time an activity can be completed without delaying the project finish date
question
late start date
answer
the latest possible time an activity may begin without delaying the project finish date
question
mandatory dependencies
answer
the sequencing of project activities or tasks that are inherent in the nature of the work being done on the project; considers unpredictive possibilties
question
merge
answer
two or more nodes that precede a single node on a network diagram
question
milstone
answer
a *significant event* that normally has no duration on a project; serves as a marker to help in identifying necessary activities, setting schedule goals and monitoring progress
question
multitasking
answer
working on more than one task at a time
question
Murphy's law
answer
the principle that if something can go wrong, it will
question
network diagram
answer
a schematic display of the logical relationships or sequencing of project activities
question
node
answer
the starting and ending point of an activity on an activity-on-arrow diagram
question
Parkinson's Law
answer
the principle that work expands to fill the time allowed
question
PERT weighted average
answer
(optimistic time + 4 * most likely time + pessimistic time)/6
question
precedence diagramming method (PDM)
answer
a network diagramming technique in which boxes represent activities
question
probabilistic time estimates
answer
duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations instead of using one specific or discrete estimate
question
Program Evaluation and Review Technique (PERT)
answer
a project network analysis technique used to estimate project duration when there is a *high degree of uncertainty* about the individual activity duration estimates
question
project buffer
answer
time added before the project's due date
question
project time management
answer
the processes required to ensure timely completion of a project
question
resource breakdown structure
answer
a hierarchical structure that identifies the project's resources by category and type
question
resources
answer
people, equipment and materials
question
schedule baseline
answer
the approved planned schedule for the project
question
slack
answer
the amount of time a project activity may be delayed without delaying a succeeding activity or the project finish date; float
question
slipped milstone
answer
a milestone activity that is completed later than planned
question
SMART criteria
answer
guidelines to help define milestones that are specific, measurable, assignable, realistic and time-framed
question
start-to-finish dependency
answer
a relationship on a project network diagram in which the "from" activity cannot start before the "to" activity is finished
question
start to start dependency
answer
a relationship on a project network diagram in which the "from" activity cannot start until the "to" activity starts
question
task/activity
answer
an element of work normally found on the WBS that has an expected *duration, cost and resource requirements*
question
Theory of Constraints (TOC)
answer
a management philosophy that any complex system at any point in time often has only one aspect or constraint that limits the ability to achieve more of the system's goal
question
three-point estimate
answer
an estimate that includes an optimistic, most likely and pessimistic estimate
question
total slack (total float)
answer
the amount of time an activity may be delayed from its early start without delaying the planned project finish date
question
Tracking Gantt chart
answer
a Gantt chart that compares *planned and actual project schedule* information
question
actual cost (AC)
answer
the total of direct and indirect costs incurred in accomplishing work on an activity during a given period
question
analogous estimates
answer
a cost-estimating technique that uses the actual cost of a previous similar project as the basis for estimating the cost of the current project; top-down estimates
question
baseline
answer
the original project plan plus approved changes
question
bottom-up estimates
answer
a cost-estimating technique based on estimating individual work items and summing them to get a project total
question
budget at completion (BAC)
answer
the original total budget for a project
question
budgetary estimate
answer
a cost estimate used to allocate money into an organization's budget
question
cash flow analysis
answer
a method for determining the estimated annual costs and benefits for a project
question
contingency reserves
answer
dollar amounts included in a cost estimate to allow for future situations that may be *partially planned for* (sometimes called known unknowns) and that are included in the project cost baseline
question
cost baseline
answer
a time-phased budget that project managers use to measure and monitor cost performance
question
cost performance index (CPI)
answer
the ratio of earned value to actual cost; can be used to estimate the projected cost to complete the project
question
cost variance (CV)
answer
the earned value minus the actual cost
question
definitive estimate
answer
a cost estimate that provides an accurate estimate of a projects cost
question
direct costs
answer
costs that can be directly related to creating the products and services of the project
question
earned value (EV)
answer
an estimate of the value of the physical work actually completed
question
earned value management (EVM)
answer
a project performance measurement technique that *integrates scope, time and cost data*
question
estimate at completion (EAC)
answer
an estimate of what it will cost to complete the project based on performance to date
question
indirect costs
answer
costs that are not directly related to the products or services of the project, but are indirectly related to performing the project
question
intangible costs or benefits
answer
costs or benefits that are difficult to measure in monetary terms
question
learning curve theory
answer
a theory that when *many items are produced repetitively, the unit cost of those items normally decreases* in a regular pattern as more units are produced
question
life cycle costing
answer
the *total cost* of ownership, or development *plus support costs*, for a project
question
management reserves
answer
dollar amounts included in a cost estimate to allow for future situations that are *unpredictable* (sometimes called unknown knowns)
question
overrun
answer
the additional percentage or dollar amount by which actual *costs exceed estimates*
question
parametric estimating
answer
a cost-estimating technique that uses project characteristics (parameters) in a mathematical model to estimate project costs
question
planned value (PV)
answer
the portion of the approved total cost estimate planned to be spent on an activity during a given period
question
profit margin
answer
the ratio between revenues and profits
question
profits
answer
revenues minus expenses
question
project cost management
answer
the processes required to ensure that the project is completed within the *approved budget*
question
rate of performance (RP)
answer
the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity
question
reserves
answer
dollar amounts included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict
question
rough order of magnitude (ROM) estimate
answer
a cost estimate prepared very early in the life of a project to provide a rough idea of what a project will cost
question
schedule performance index (SPI)
answer
the ratio of earned value to planned value; can be used to estimate the projected time to complete a project
question
schedule variance (SV)
answer
the earned value minus the planned value
question
sunk cost
answer
money that has been spent in the past
question
tangible costs or benefits
answer
costs or benefits that can be easily measured in dollars
question
5 whys
answer
a technique in which you repeatedly ask the question "Why?" to help peel away the layers of symptoms that can *lead to the root cause of a problem*
question
acceptance decisions
answer
decisions that determine if the products or services produced as part of the project will be accepted or rejected
question
appraisal cost
answer
the cost of evaluating processes and their outputs to ensure that a project is error-free or within an acceptable error range
question
Capability Maturity Model Integration (CMMI)
answer
a process improvement approach that provides organizations with the essential elements of effective processes
question
cause and effect diagram
answer
a diagram that traces complaints about quality programs back to the responsible production operations to help find the root cause; fishbone diagram or Ishikawa diagram
question
checksheet
answer
a technique used to collect and analyze data; tally sheet or checklist
question
conformance
answer
delivering products that meet requirements and fitness for all
question
conformance to requirements
answer
project processes and products that *meet written specifications*
question
control chart
answer
a graphic display of data that illustrates the results of a process over time
question
cost of nonconformance
answer
taking responsibility for failures or not meeting quality expectations
question
cost of quality
answer
the cost of conformance plus the cost of nonconformance
question
defect
answer
any instance in which the the product or service *fails to meet customer requirements*
question
design of experiments
answer
a quality technique that helps identify which variables have the most influence on the overall outcome of a process
question
DMAIC
answer
Define, measure, analyze, improve, control a systematic, closed-loop process for continued improvement that is scientific and fact based
question
external failure cost
answer
a cost related to all errors that are not detected and corrected before delivery to the customer
question
features
answer
the special characteristics that appeal to users
question
fitness for use
answer
a product that can be used as it was *intended*
question
flowchart
answer
a graphic display of the logic and flow of processes that helps you analyze how problems occur and how processes can be improved
question
functionality
answer
the degree to which a system performs its *intended function*
question
histogram
answer
a bar graph of a distribution of variables
question
integration testing
answer
testing that occurs between unit and system testing to test functionally *grouped components* and ensure that a subset or subsets of the entire system work together
question
internal failure cost
answer
a cost incurred to correct an identified defect *before* the customer receives the product
question
ISO 9000
answer
A quality system standard developed by the International Organization for Standardization (ISO) that includes a three-part, continuous cycle of planning, controlling and documenting quality in an org
question
kaizen
answer
the Japanese word for *improvement* or change for the better; an approach used for continuously improving quality in orgs
question
lean
answer
an approach for improving quality that involves evaluating processes to *maximize customer value* while *minimizing waste*
question
maintainability
answer
the ease of performing maintenance on a product
question
Malcolm Baldrige National Quality Award
answer
an award started in 1987 to recognize companies that have achieved a level of word-class competition through quality management
question
maturity model
answer
a framework for helping organizations improve their processes and systems
question
mean
answer
average value of the population
question
measurement and test equipment costs
answer
the capital cost of equipment used to perform prevention and appraisal activities
question
metric
answer
a standard of measurement
question
normal distribution
answer
bell-shaped curve that is symmetrical about the mean of the population
question
Pareto analysis
answer
identifying the vital few contributors that account for most quality problems in a system
question
Pareto chart
answer
histogram that helps identify and prioritize problem areas
question
performance
answer
how well a product or service *performs the customer's intended use*
question
prevention cost
answer
the cost of planning and executing a project so that it is error-free or within an acceptable error range
question
process adjustments
answer
adjustments made to correct or prevent further quality problems based on quality control measurements
question
project quality management
answer
ensuring that a project will satisfy the *needs for which it was undertaken*
question
quality
answer
the totality of characteristic of an entity that bear on its ability to satisfy stated or implied needs or the degree to which a set of inherent characteristics fulfill requirements
question
quality assurance
answer
periodic evaluation of overall project performance to ensure that the project will satisfy the relevant quality standards
question
quality audit
answer
a *structured review* of specific quality management activities that helps identify lessons learned and that can improve performance on current or future projects
question
quality circles
answer
groups of nonsupervisors and work leaders in a single company department who volunteer to conduct group studies on how to improve the effectiveness of work in their department
question
quality control
answer
monitoring specific project results to ensure that they comply with the relevant quality standards and identifying ways to improve overall quality
question
reliability
answer
the ability of a product or service to *perform as expected under normal conditions*
question
rework
answer
action taken to *bring rejected items into compliance* with product requirements, specifications or other stakeholder expectations
question
Robust Design Methods
answer
methods that focus on eliminating defects by substituting scientific inquiry for trial and error methods.
question
run chart
answer
a chart that displays the history and pattern of variation of a process over time
question
scatter diagram
answer
a diagram that helps to show if their is a relationship between two variables; XY charts
question
seven run rule
answer
if seven data points in a row on a quality control chart are all below the mean, above the mean or all increasing or decreasing, then the process needs to be examined for *nonrandom problems*
question
six 9s of quality
answer
a measure of quality control equal to 1 fault in 1 million opportunities
question
Six Sigma
answer
a comprehensive and flexible system for achieving, sustaining, and maximizing business success that is uniquely driven by close understanding of customer needs, disciplined use of facts, data and statistical analysis, and diligent attention to managing, improving and reinventing business processes
question
standard deviation
answer
measure of how much variation exists in a distribution of data
question
statistical sampling
answer
choosing part of a population of interest for inspection
question
system outputs
answer
the screens and reports the system generates
question
system testing
answer
testing the entire system as one entity to ensure that it is working properly
question
unit test
answer
a test of each individual component (often a program) to ensure that it is as defect free as possible
question
user acceptance testing
answer
an independent test performed by end users prior to accepting the delivered system
question
yield
answer
the number of units handled correctly through the development process