1. For a project manager, monitoring ____
answer
b. includes monitoring progress of the project, evaluating results, and taking corrective action when necessary to stay on target
question
2. Project scheduling involves all of the following except
answer
a. defining project constraints
question
3. PERT/CPM is called a ___ technique, because it analyzes a large, complex project as a series of individual tasks
answer
b. bottom-up
question
4. the first step in the creation of a PERT/CPM chart is to
answer
c. identify all of the project tasks
question
5. the first step in creating a WBS is to
answer
c. identify all tasks
question
6. In addition to tasks, every project has ___, which are reference points used to monitor progress and manage the project
answer
b. milestones
question
7. two or more concurrent task often depend on a single prior task, which is called a __ task
answer
a. predecessor
question
8. When two or more concurrent tasks depend on a single prior task, the noncurrent tasks are called ___ tasks
answer
b. successor
question
9. a ___ path includes all task that are vital to the project schedule
answer
c. critical
question
10. ___ is a open-source software that is supported by a large group of users and developers
answer
a. Open work-bench
question
11. A ____ cannot be started until one or more other tasks are completed
answer
a. dependent task